From: Chris waller on 9 May 2008 08:01 I am trying to use the Adjust Dates button to advance an MS Project 2000; however there appears to be a problem with some tasks which take place over the weekend. I have created a calendar which I have called weekend and I have made Saturday and Sunday the only working days and I have allocated the appropriate tasks to this calendar. The problem is that when I look on the Gannt Chart the weekends where there is work have not moved as predicted. I am sure that I am doing something wrong, but I have only been using Project for a couple of weeks. Thanks in advance.
From: Jack Dahlgren on 9 May 2008 17:36
Chris, Take a look at your calendar and make sure the the weekends are there for each month. Sometimes people make changes which do not go far enough into the future and don't realize it. -Jack Dahlgren "Chris waller" wrote: > I am trying to use the Adjust Dates button to advance an MS Project 2000; > however there appears to be a problem with some tasks which take place over > the weekend. I have created a calendar which I have called weekend and I have > made Saturday and Sunday the only working days and I have allocated the > appropriate tasks to this calendar. The problem is that when I look on the > Gannt Chart the weekends where there is work have not moved as predicted. I > am sure that I am doing something wrong, but I have only been using Project > for a couple of weeks. > Thanks in advance. > |