From: Joe Martocci on 26 Oct 2005 13:31 A customer of mine has asked me to graph when we can expect our project to catch up with the baseline. I've adjusted some durations and task relationships on how we plan to catch up. I then set the "Status Date" to the end project date and set all tasks to 100%. My thinking is that if we complete all the tasks based on the new schedule, I should see BCWP catch up to BCWS. However, when I do this and export the values to Excel, the time phased BCWP doesn't equal the BCWS. I thought when all the tasks were complete, the BCWP would equal the BCWS? What's going on? Thanks,
|