|
From: "Rob Fisher" <Rob on 24 Oct 2005 10:58 Both of these fields are zero. I have baselined the plan and have set the status date to today's date. Tools=>Options=>Calculation Updating Task Status Updates Resource Status box checked. I have resources assigned to tasks with standard and overtime rates input. Resources are assigned to tasks. Where am I going wrong?
From: "JulieS" <passport6847 at maine dot rr dot on 24 Oct 2005 17:20 Hi Rob, For BCWS: Were the tasks scheduled to have any work as of the status date? If the tasks are in the future, BCWS will be zero until the status date is equal to or later than the baseline start date of the task. From Help: ================================== How Calculated To calculate BCWS for a task, Microsoft Office Project 2003 adds the timephased baseline costs of the task up to the status date. ================================== For BCWP: Have you recorded any actual work against the tasks? BCWP is not calculated until you enter Actual Work. From Help: ==================================== How Calculated When a task is first created, the BCWP is 0.00. As soon as a baseline is saved and progress is reported for the task (as actual work, actual duration, or percentage of work complete), Microsoft Office Project 2003 calculates BCWP. Hope this helps. Let us know how you get along. Julie "Rob Fisher" <Rob Fisher(a)discussions.microsoft.com> wrote in message news:925C43D2-8348-4AF8-8A7E-6EBB41569894(a)microsoft.com... > Both of these fields are zero. I have baselined the plan and have set the > status date to today's date. > Tools=>Options=>Calculation Updating Task Status Updates Resource Status > box > checked. > I have resources assigned to tasks with standard and overtime rates input. > Resources are assigned to tasks. > Where am I going wrong?
|
Pages: 1 Prev: Planned Value Next: Change format for Visio WBS Chart Wizard in MS Project to Process |