|
From: Balroc on 13 May 2008 18:58 I'm trying to define a task that can occur in a wide time window relative to the work effort involved. Let's say that I have a design spec that's drafted and then sent out for review. The review period is 30 days and I want to assign tasks for people to read the spec and approve or deny it. There's 3 people and I want to assign them each a task with a 1/2 day duration to do this action, but I don't care when they do so in the 30 day review period. If I set up the task with a .5d duration and start/end dates that are 30 days apart, project will either change the start/end dates or increase the duration. How can I get past this? TIA
From: Jack Dahlgren on 13 May 2008 20:14 I'd not bother to model tasks of less than a day of duration. It sounds as if the review is not time critical so why bother putting it in the schedule? -Jack Dahlgren "Balroc" <liametavirp(a)yahoo.com> wrote in message news:eKjka0UtIHA.1768(a)TK2MSFTNGP03.phx.gbl... > I'm trying to define a task that can occur in a wide time window relative > to the work effort involved. Let's say that I have a design spec that's > drafted and then sent out for review. The review period is 30 days and I > want to assign tasks for people to read the spec and approve or deny it. > There's 3 people and I want to assign them each a task with a 1/2 day > duration to do this action, but I don't care when they do so in the 30 day > review period. If I set up the task with a .5d duration and start/end > dates that are 30 days apart, project will either change the start/end > dates or increase the duration. How can I get past this? > > TIA
From: Balroc on 13 May 2008 20:27 It's a hypothetical scenario. Make it a 5 days of review over a 30 day window. "Jack Dahlgren" <jack(a)zo-d.com> wrote in message news:uDv9HdVtIHA.3780(a)TK2MSFTNGP03.phx.gbl... > I'd not bother to model tasks of less than a day of duration. > It sounds as if the review is not time critical so why bother putting it > in the schedule? > > -Jack Dahlgren > > "Balroc" <liametavirp(a)yahoo.com> wrote in message > news:eKjka0UtIHA.1768(a)TK2MSFTNGP03.phx.gbl... >> I'm trying to define a task that can occur in a wide time window relative >> to the work effort involved. Let's say that I have a design spec that's >> drafted and then sent out for review. The review period is 30 days and I >> want to assign tasks for people to read the spec and approve or deny it. >> There's 3 people and I want to assign them each a task with a 1/2 day >> duration to do this action, but I don't care when they do so in the 30 >> day review period. If I set up the task with a .5d duration and >> start/end dates that are 30 days apart, project will either change the >> start/end dates or increase the duration. How can I get past this? >> >> TIA > >
From: Jack Dahlgren on 13 May 2008 21:45 Then set duration to 30d and work to 5d. It should give a units of 17% or so. -Jack Dahlgren "Balroc" <liametavirp(a)yahoo.com> wrote in message news:eBE$FmVtIHA.4772(a)TK2MSFTNGP03.phx.gbl... > It's a hypothetical scenario. Make it a 5 days of review over a 30 day > window. > "Jack Dahlgren" <jack(a)zo-d.com> wrote in message > news:uDv9HdVtIHA.3780(a)TK2MSFTNGP03.phx.gbl... >> I'd not bother to model tasks of less than a day of duration. >> It sounds as if the review is not time critical so why bother putting it >> in the schedule? >> >> -Jack Dahlgren >> >> "Balroc" <liametavirp(a)yahoo.com> wrote in message >> news:eKjka0UtIHA.1768(a)TK2MSFTNGP03.phx.gbl... >>> I'm trying to define a task that can occur in a wide time window >>> relative to the work effort involved. Let's say that I have a design >>> spec that's drafted and then sent out for review. The review period is >>> 30 days and I want to assign tasks for people to read the spec and >>> approve or deny it. There's 3 people and I want to assign them each a >>> task with a 1/2 day duration to do this action, but I don't care when >>> they do so in the 30 day review period. If I set up the task with a .5d >>> duration and start/end dates that are 30 days apart, project will either >>> change the start/end dates or increase the duration. How can I get past >>> this? >>> >>> TIA >> >> >
From: "Steve House" sjhouse at hotmail dot on 16 May 2008 06:17 You're trying to redefine the metrics that Project uses, calling an apple an orange. Duration is BY DEFINITION the amount of time between when the task begins and when it ends, with intervening non-working time periods as defined in the working time calendar deducted. (A task beginning 8am 02 June and ending 5pm 27 June has a 20 day duration, not 25, because the weekends don't count.) Your example task is neither 1/2 day task nor a 1.5 day task, it is a 30 day task and you simply have to live with that. Work, on the other hand, is the amount of the duration that the resource(s) spend in observable physical acvitity on the task. Work and duration are related to each other based on the rate at which the resource converts time into work, that is, the assignment units, through the identity W=D*U. Your example is of a 30 day duration task has 6 weeks elapsing between start date and finish date task requiring 12 man-hours of work resulting in a resource assignment level of 12 man-hours/240 hours/3 resources =1.6% I think when you say it has a 30 day review period you really mean 30 calendar days, ie the month of June, and not 30 duration (working) days. If so, the real number for your task would be more like: Start 02 June, End 30 June, Duration 21 days, Work 12 hours, Units 2.3% You'll do a much better job of scheduling if you abandon altogether the idea of duration as being the "window of opportunity" within which the resource should work on the task and instead get more proactive and precise: "Joe, that widget will be ready for you to work on next Tuesday - it should take you a about a half-day - is that right? - so can I tell Mary you'll for sure be passing it on to her no later than Thursday?" Durations, IMHO, should represent your best estimate of what it WILL take, not the maximum that it COULD take. So your example task would become a 1/2 day task able to start 02 June with a deadline of 30 June. -- Steve House [Project MVP] MS Project Trainer & Consultant Visit http://project.mvps.org/faqs.htm for the FAQs "Balroc" <liametavirp(a)yahoo.com> wrote in message news:eKjka0UtIHA.1768(a)TK2MSFTNGP03.phx.gbl... > I'm trying to define a task that can occur in a wide time window relative > to the work effort involved. Let's say that I have a design spec that's > drafted and then sent out for review. The review period is 30 days and I > want to assign tasks for people to read the spec and approve or deny it. > There's 3 people and I want to assign them each a task with a 1/2 day > duration to do this action, but I don't care when they do so in the 30 day > review period. If I set up the task with a .5d duration and start/end > dates that are 30 days apart, project will either change the start/end > dates or 4 > increase the duration. How can I get past this? > > TIA
|
Pages: 1 Prev: Import reoccuring Task from excel- import map Next: %Complete |