From: Mike on
I have used the Baseline and Baseline 1 fields in my schedule. However,
there is only a cost spread for the regular work and baseline work.



Any explanation as to why there is not a spread for the baseline 1 work?
From: JulieS on
Mike,

What version (including Service pack) of Project are you using? With
Project 2003 SP-3 I see both Work, Cost, Baseline Cost, Baseline Work
and Baseline1 Cost and Baseline1 work in the Task Usage view. Are you
using Cost resources or work resources with costs?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Mike" <Mike(a)discussions.microsoft.com> wrote in message
news:73518319-D1BD-4EC5-AF6E-7656224B31CF(a)microsoft.com...
>I have used the Baseline and Baseline 1 fields in my schedule.
>However,
> there is only a cost spread for the regular work and baseline work.
>
>
>
> Any explanation as to why there is not a spread for the baseline 1
> work?


From: Mike on
Hi Julie

I am running 2 versions on one laptop. the schedule i am dealing with here
is in MS project 2007 with SP1 MSO.

Using work resources with cost.

Thanks


"JulieS" wrote:

> Mike,
>
> What version (including Service pack) of Project are you using? With
> Project 2003 SP-3 I see both Work, Cost, Baseline Cost, Baseline Work
> and Baseline1 Cost and Baseline1 work in the Task Usage view. Are you
> using Cost resources or work resources with costs?
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
>
> "Mike" <Mike(a)discussions.microsoft.com> wrote in message
> news:73518319-D1BD-4EC5-AF6E-7656224B31CF(a)microsoft.com...
> >I have used the Baseline and Baseline 1 fields in my schedule.
> >However,
> > there is only a cost spread for the regular work and baseline work.
> >
> >
> >
> > Any explanation as to why there is not a spread for the baseline 1
> > work?
>
>
>
From: JulieS on
Hi Mike,

Sorry, I can't reproduce what you report using Project 2007 SP-1. If
I create a simple project, assign resources with costs and save a
baseline in the Task Usage view I see:
Work
Cost
Baseline Work
Baseline Cost

I change the work value and save as Baseline1. I see cost for both
Baseline and Baseline 1.

Is this happening on all projects (create a quick test) or only one
project? Was the project created in Prj 2007 or the earlier version?

Julie

"Mike" <Mike(a)discussions.microsoft.com> wrote in message
news:68E5ED90-63AA-4A08-B566-8DE1DA377442(a)microsoft.com...
> Hi Julie
>
> I am running 2 versions on one laptop. the schedule i am dealing
> with here
> is in MS project 2007 with SP1 MSO.
>
> Using work resources with cost.
>
> Thanks
>
>
> "JulieS" wrote:
>
>> Mike,
>>
>> What version (including Service pack) of Project are you using?
>> With
>> Project 2003 SP-3 I see both Work, Cost, Baseline Cost, Baseline
>> Work
>> and Baseline1 Cost and Baseline1 work in the Task Usage view. Are
>> you
>> using Cost resources or work resources with costs?
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information
>> about Microsoft Project
>>
>>
>> "Mike" <Mike(a)discussions.microsoft.com> wrote in message
>> news:73518319-D1BD-4EC5-AF6E-7656224B31CF(a)microsoft.com...
>> >I have used the Baseline and Baseline 1 fields in my schedule.
>> >However,
>> > there is only a cost spread for the regular work and baseline
>> > work.
>> >
>> >
>> >
>> > Any explanation as to why there is not a spread for the baseline
>> > 1
>> > work?
>>
>>
>>