From: okindb on 25 Apr 2008 12:17 How can I utilize Project to determine my crew size if I know my task durations and budgeted hours for each task?
From: Trevor Rabey on 25 Apr 2008 13:20 Estimate the Duration, then throw the Resources that you think you might need at the Task. Then check the Work Table. If the hours are more or less than your budget hours, decide what to do about it, such as reduce or increase the Resource units. This includes the possibility of revising the budget. Trevor RabeyTrevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "okindb" <okindb(a)discussions.microsoft.com> wrote in message news:0191F820-1B79-4184-A8FD-573E12332859(a)microsoft.com... > How can I utilize Project to determine my crew size if I know my task > durations and budgeted hours for each task?
|