From: Matt Schiemer on
I need help with getting the "duration" of 1month to equal one calendar month
in terms of start and finish times. When I set the calendar to a 7 day work
week it seems to work for a duration set in days (i.e., 365 day duration with
1/1/06 start date will show end date of 12/31/06), but if I input a duration
of 12 months for that same 1/1/06 start date, it goes from 1/1/06 to 1/7/07.
Why won't 12 months also finish on 12/31/06?? How can I get one month to
equal one month??

Thanks in advance for your help.
From: John on
In article <0833DFFD-DCD0-4715-90D4-2CCE3697BE8B(a)microsoft.com>,
"Matt Schiemer" <MattSchiemer(a)discussions.microsoft.com> wrote:

> I need help with getting the "duration" of 1month to equal one calendar month
> in terms of start and finish times. When I set the calendar to a 7 day work
> week it seems to work for a duration set in days (i.e., 365 day duration with
> 1/1/06 start date will show end date of 12/31/06), but if I input a duration
> of 12 months for that same 1/1/06 start date, it goes from 1/1/06 to 1/7/07.
> Why won't 12 months also finish on 12/31/06?? How can I get one month to
> equal one month??
>
> Thanks in advance for your help.

Matt,
Because Project does not use a lunar calendar. That is, some months have
30 days and most others have 31. However the real answer to your
question is a settings found under Tools/Options/Calendar tab. The
setting for "Days per month" is based on a default 20 working days per
month and that's what Project uses when it calculates duration in
months. You could reset it to be 30 days per month but then it wouldn't
track with Feb, Mar, May, etc.

Not the answer you were looking for but if you want more-or-less exact
durations, use "days". You can set the duration to be elapsed days if
you want. To do that add "ed" to the Duration value.

John
Project MVP
From: Matt Schiemer on
Thanks, John. I'm very surprised that Project can't deal with lunar (normal)
calendar months. I've noticed several other comments/questions regarding
this issue -- hopefully it's something that Microsoft can build into future
versions...

Thanks again.

"John" wrote:

> In article <0833DFFD-DCD0-4715-90D4-2CCE3697BE8B(a)microsoft.com>,
> "Matt Schiemer" <MattSchiemer(a)discussions.microsoft.com> wrote:
>
> > I need help with getting the "duration" of 1month to equal one calendar month
> > in terms of start and finish times. When I set the calendar to a 7 day work
> > week it seems to work for a duration set in days (i.e., 365 day duration with
> > 1/1/06 start date will show end date of 12/31/06), but if I input a duration
> > of 12 months for that same 1/1/06 start date, it goes from 1/1/06 to 1/7/07.
> > Why won't 12 months also finish on 12/31/06?? How can I get one month to
> > equal one month??
> >
> > Thanks in advance for your help.
>
> Matt,
> Because Project does not use a lunar calendar. That is, some months have
> 30 days and most others have 31. However the real answer to your
> question is a settings found under Tools/Options/Calendar tab. The
> setting for "Days per month" is based on a default 20 working days per
> month and that's what Project uses when it calculates duration in
> months. You could reset it to be 30 days per month but then it wouldn't
> track with Feb, Mar, May, etc.
>
> Not the answer you were looking for but if you want more-or-less exact
> durations, use "days". You can set the duration to be elapsed days if
> you want. To do that add "ed" to the Duration value.
>
> John
> Project MVP
>
From: John on
In article <E48F9018-1A7B-480B-8C04-A081AFA9B235(a)microsoft.com>,
"Matt Schiemer" <MattSchiemer(a)discussions.microsoft.com> wrote:

> Thanks, John. I'm very surprised that Project can't deal with lunar (normal)
> calendar months. I've noticed several other comments/questions regarding
> this issue -- hopefully it's something that Microsoft can build into future
> versions...
>
> Thanks again.

Matt,
You're welcome. If enough people request a feature, I'd say there is a
good change a future version will incorporate it.

John
>
> "John" wrote:
>
> > In article <0833DFFD-DCD0-4715-90D4-2CCE3697BE8B(a)microsoft.com>,
> > "Matt Schiemer" <MattSchiemer(a)discussions.microsoft.com> wrote:
> >
> > > I need help with getting the "duration" of 1month to equal one calendar
> > > month
> > > in terms of start and finish times. When I set the calendar to a 7 day
> > > work
> > > week it seems to work for a duration set in days (i.e., 365 day duration
> > > with
> > > 1/1/06 start date will show end date of 12/31/06), but if I input a
> > > duration
> > > of 12 months for that same 1/1/06 start date, it goes from 1/1/06 to
> > > 1/7/07.
> > > Why won't 12 months also finish on 12/31/06?? How can I get one month
> > > to
> > > equal one month??
> > >
> > > Thanks in advance for your help.
> >
> > Matt,
> > Because Project does not use a lunar calendar. That is, some months have
> > 30 days and most others have 31. However the real answer to your
> > question is a settings found under Tools/Options/Calendar tab. The
> > setting for "Days per month" is based on a default 20 working days per
> > month and that's what Project uses when it calculates duration in
> > months. You could reset it to be 30 days per month but then it wouldn't
> > track with Feb, Mar, May, etc.
> >
> > Not the answer you were looking for but if you want more-or-less exact
> > durations, use "days". You can set the duration to be elapsed days if
> > you want. To do that add "ed" to the Duration value.
> >
> > John
> > Project MVP
> >
From: Steve House [Project MVP] on
The reason is that duration only includes working time, not elapsed time.
The same thing happens with a "day." A duration day is not 24 hours, the
time between one sunrise and another. It is a working day, typically 8
hours, the time that passes between when an individual resource comes in to
work and when he goes home for the day. The elapsed hours when that
resource is not there during a day or a week or a month simply don't count
for duration. For planning purposes they might as well not exist at all. A
basic question Project seeks to answer is "If task X requires this many
man-hours of effort to achieve its results and we can start on Monday, when
will we finish it?" Only times when people are physically present working
will count to burning up required effort hours. Nothing happens during
non-working time and so no progress is made during those hours. As a
result, saying "I expect this task to take 3 calendar months" doesn't really
convey any information about the task since it fails to take into account
how much of that 3 months is productive time and how much is non-productive
time. Remember Project tracks everything down to the minute and the ability
even to use months as a unit in the first place is structly there as a
convenience for planning to a very rough crude approximation. When you get
to planning the real schedule you need to be thinking in smaller units than
that. - I like to remember the 8/80 rule, which says tasks should be longer
than 8 hours but less than 80 - over 80 you're not planning in enough detail
to effectively manage the work and under 8 you're meddling excessively in
the resource's workday. There are exceptions to that, of course, but it's
still a pretty good guideline.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



"Matt Schiemer" <MattSchiemer(a)discussions.microsoft.com> wrote in message
news:E48F9018-1A7B-480B-8C04-A081AFA9B235(a)microsoft.com...
> Thanks, John. I'm very surprised that Project can't deal with lunar
> (normal)
> calendar months. I've noticed several other comments/questions regarding
> this issue -- hopefully it's something that Microsoft can build into
> future
> versions...
>
> Thanks again.
>
> "John" wrote:
>
>> In article <0833DFFD-DCD0-4715-90D4-2CCE3697BE8B(a)microsoft.com>,
>> "Matt Schiemer" <MattSchiemer(a)discussions.microsoft.com> wrote:
>>
>> > I need help with getting the "duration" of 1month to equal one calendar
>> > month
>> > in terms of start and finish times. When I set the calendar to a 7 day
>> > work
>> > week it seems to work for a duration set in days (i.e., 365 day
>> > duration with
>> > 1/1/06 start date will show end date of 12/31/06), but if I input a
>> > duration
>> > of 12 months for that same 1/1/06 start date, it goes from 1/1/06 to
>> > 1/7/07.
>> > Why won't 12 months also finish on 12/31/06?? How can I get one month
>> > to
>> > equal one month??
>> >
>> > Thanks in advance for your help.
>>
>> Matt,
>> Because Project does not use a lunar calendar. That is, some months have
>> 30 days and most others have 31. However the real answer to your
>> question is a settings found under Tools/Options/Calendar tab. The
>> setting for "Days per month" is based on a default 20 working days per
>> month and that's what Project uses when it calculates duration in
>> months. You could reset it to be 30 days per month but then it wouldn't
>> track with Feb, Mar, May, etc.
>>
>> Not the answer you were looking for but if you want more-or-less exact
>> durations, use "days". You can set the duration to be elapsed days if
>> you want. To do that add "ed" to the Duration value.
>>
>> John
>> Project MVP
>>