|
From: CDAK95 on 13 Jan 2006 11:48 Thanks, Steve. I think what I would prefer to see is Elapsed Calendar days, as opposed to Duration. Is there a field that provides this information? "Steve House [Project MVP]" wrote: > That's not really an accurate way of doing it. What the % represents is the > portion of the resource's work time that gets converted into useful work. > If the workday is set to 10 hours and you assign the resource to a 1 day > task at 65%, it does NOT mean they're present for 6.5 hours. It means > they're physically present and working on the task for the full 10 hours but > for some reason - perhaps they're distracted talking about the Superbowl > with their buddies on the job - they're only getting 6.5 hours worth of > full-time equivalent work output accomplished. IMHO the best way do it is > to set the Project calendar and option settings to that of the most generic > schedule, or perhaps the official schedule of the managment office. Workers > who deviate from that schedule have their own modified calendars - resource > calendars - that reflect their actual hours of work. "Day's" does not > equate to "come-to-works." A part-timer who works 4 hours per day has to > come to work TWICE to get one day's work accomplished while someone who is > scheduled 12 hours on and 12 hours off does one and a half day's work each > time he comes to the property. The word "day" should be interpretted as > "one standard shift" and not "one sunrise." By that logic, a plant that > works 24/7 works 3 days duration for every 24 hour normal sunrise-to-sunrise > civil calendar day. > -- > Steve House [MVP] > MS Project Trainer & Consultant > Visit http://www.mvps.org/project/faqs.htm for the FAQs > > > > "CDAK95" <CDAK95(a)discussions.microsoft.com> wrote in message > news:FA0CB592-1289-4A3C-8B9D-E05DD26062EC(a)microsoft.com... > >I am working my way around this by establishing my project calendar day as > >10 > > hours. For the individuals who work a 6.5 hour day, I set their > > availability > > as 65% in the resource sheet. Similarly, I set my resources on the 8.5 > > hour > > schedule with 85% availability. Will this cause me grief in the Gantt > > chart? > > > > "Steve House [Project MVP]" wrote: > > > >> Duration is always measured in hours (actually 10ths of minutes if you > >> want > >> to get technical). Durations expressed as days, weeks, months, etc are > >> strictly conversions for convenience. The number of hours that is > >> considered "1 day" is a global setting controlled by the Hours per Day > >> field > >> on the Tools, Options, Calendar page. The actual elapsed timed that > >> transpires from when the task begins until it ends is calculated using > >> the > >> calendar that controls that task - the Project Calendar that for tasks > >> that > >> do not have resources assigned and the Resource task for the assigned > >> resource for tasks that do. > >> > >> Example: > >> > >> In a project starting Monday at 8am with all the default settings I enter > >> a > >> task as having "1 day" duration. 1 day = 8 hours so the "real" duration > >> of > >> the task is 8 hours. The standard project calendar has an 8 hour work > >> day. > >> The task begins at 8am and ends 8 working hours later, at 5pm. I assign > >> that task to a (very) part-time resource who works only 1 hour per day > >> over > >> the lunch hour, Mon thru Fri. His work calendar shows hours of work as > >> 12noon to 1pm, M-F. When I assign that task to him, it moves to start > >> when > >> he comes in to work, 12noon on Monday. It ends when 8 of HIS working > >> hours > >> have elapsed, at 1pm on Wednesday a week and a half later. That is still > >> a > >> "1 day" task because the phrase "1 day duration" really means "how ever > >> long > >> it takes to have been on the job for 8 working hours" (okay, 4800 > >> deciminutes if you want to be picky <grin>) and that's what the duration > >> in > >> the Gantt chart will show. > >> -- > >> Steve House [MVP] > >> MS Project Trainer & Consultant > >> Visit http://www.mvps.org/project/faqs.htm for the FAQs > >> > >> > >> "CDAK95" <CDAK95(a)discussions.microsoft.com> wrote in message > >> news:75DA5500-8F2E-4D40-B345-3B1BBDFBDF25(a)microsoft.com... > >> > Within my project, I have several resource groups that have different > >> > schedules (i.e. one group work 6.5 hours per day x 5 days, the second > >> > group > >> > works 8.5 hours per day x 7 days, and the third group works 10 hours > >> > per > >> > day > >> > x 7 days). I have set up seperate calendars for each group. However, > >> > it > >> > appears the duration is calculated based upon a common calendar. How > >> > can > >> > I > >> > change this function so it calculates duration based upon the work > >> > calendar > >> > specific to each working group? > >> > >> > >
From: "JulieS" <passport6847 at maine dot rr dot on 14 Jan 2006 08:30
Hi CDAK95, You can use a custom duration field to calculate how many calendar days there are between the start of a task and the finish. Create a new calendar (Tools>Change Working Time). Copy the Standard calendar, name it (I used 7Day) and make Saturdays & Sundays working days. Then insert a custom duration field ([Duration1] for example) in the task table. Choose Tools>Customize Fields and select the [Duration1] field. Click the Formula... button and use the following formula: ProjDateDiff([Start],[Finish],"7Day") In the Customize fields dialog box, click the Use Formula option for the task and group summary rows. This will calculate the number of calendar days between the start of the task and the finish of the task using the 7Day calendar. . I hope this helps. Let us know how you get along. Julie "CDAK95" <CDAK95(a)discussions.microsoft.com> wrote in message news:1DBF2B6C-951A-4C4C-8DEE-F229482A7098(a)microsoft.com... > Thanks, Steve. I think what I would prefer to see is Elapsed Calendar > days, > as opposed to Duration. Is there a field that provides this information? > > "Steve House [Project MVP]" wrote: > >> That's not really an accurate way of doing it. What the % represents is >> the >> portion of the resource's work time that gets converted into useful work. >> If the workday is set to 10 hours and you assign the resource to a 1 day >> task at 65%, it does NOT mean they're present for 6.5 hours. It means >> they're physically present and working on the task for the full 10 hours >> but >> for some reason - perhaps they're distracted talking about the Superbowl >> with their buddies on the job - they're only getting 6.5 hours worth of >> full-time equivalent work output accomplished. IMHO the best way do it >> is >> to set the Project calendar and option settings to that of the most >> generic >> schedule, or perhaps the official schedule of the managment office. >> Workers >> who deviate from that schedule have their own modified calendars - >> resource >> calendars - that reflect their actual hours of work. "Day's" does not >> equate to "come-to-works." A part-timer who works 4 hours per day has to >> come to work TWICE to get one day's work accomplished while someone who >> is >> scheduled 12 hours on and 12 hours off does one and a half day's work >> each >> time he comes to the property. The word "day" should be interpretted as >> "one standard shift" and not "one sunrise." By that logic, a plant that >> works 24/7 works 3 days duration for every 24 hour normal >> sunrise-to-sunrise >> civil calendar day. >> -- >> Steve House [MVP] >> MS Project Trainer & Consultant >> Visit http://www.mvps.org/project/faqs.htm for the FAQs >> >> >> >> "CDAK95" <CDAK95(a)discussions.microsoft.com> wrote in message >> news:FA0CB592-1289-4A3C-8B9D-E05DD26062EC(a)microsoft.com... >> >I am working my way around this by establishing my project calendar day >> >as >> >10 >> > hours. For the individuals who work a 6.5 hour day, I set their >> > availability >> > as 65% in the resource sheet. Similarly, I set my resources on the 8.5 >> > hour >> > schedule with 85% availability. Will this cause me grief in the Gantt >> > chart? >> > >> > "Steve House [Project MVP]" wrote: >> > >> >> Duration is always measured in hours (actually 10ths of minutes if you >> >> want >> >> to get technical). Durations expressed as days, weeks, months, etc >> >> are >> >> strictly conversions for convenience. The number of hours that is >> >> considered "1 day" is a global setting controlled by the Hours per Day >> >> field >> >> on the Tools, Options, Calendar page. The actual elapsed timed that >> >> transpires from when the task begins until it ends is calculated using >> >> the >> >> calendar that controls that task - the Project Calendar that for tasks >> >> that >> >> do not have resources assigned and the Resource task for the assigned >> >> resource for tasks that do. >> >> >> >> Example: >> >> >> >> In a project starting Monday at 8am with all the default settings I >> >> enter >> >> a >> >> task as having "1 day" duration. 1 day = 8 hours so the "real" >> >> duration >> >> of >> >> the task is 8 hours. The standard project calendar has an 8 hour work >> >> day. >> >> The task begins at 8am and ends 8 working hours later, at 5pm. I >> >> assign >> >> that task to a (very) part-time resource who works only 1 hour per day >> >> over >> >> the lunch hour, Mon thru Fri. His work calendar shows hours of work >> >> as >> >> 12noon to 1pm, M-F. When I assign that task to him, it moves to start >> >> when >> >> he comes in to work, 12noon on Monday. It ends when 8 of HIS working >> >> hours >> >> have elapsed, at 1pm on Wednesday a week and a half later. That is >> >> still >> >> a >> >> "1 day" task because the phrase "1 day duration" really means "how >> >> ever >> >> long >> >> it takes to have been on the job for 8 working hours" (okay, 4800 >> >> deciminutes if you want to be picky <grin>) and that's what the >> >> duration >> >> in >> >> the Gantt chart will show. >> >> -- >> >> Steve House [MVP] >> >> MS Project Trainer & Consultant >> >> Visit http://www.mvps.org/project/faqs.htm for the FAQs >> >> >> >> >> >> "CDAK95" <CDAK95(a)discussions.microsoft.com> wrote in message >> >> news:75DA5500-8F2E-4D40-B345-3B1BBDFBDF25(a)microsoft.com... >> >> > Within my project, I have several resource groups that have >> >> > different >> >> > schedules (i.e. one group work 6.5 hours per day x 5 days, the >> >> > second >> >> > group >> >> > works 8.5 hours per day x 7 days, and the third group works 10 hours >> >> > per >> >> > day >> >> > x 7 days). I have set up seperate calendars for each group. >> >> > However, >> >> > it >> >> > appears the duration is calculated based upon a common calendar. >> >> > How >> >> > can >> >> > I >> >> > change this function so it calculates duration based upon the work >> >> > calendar >> >> > specific to each working group? >> >> >> >> >> >> |