|
From: BurnChrome on 11 Nov 2005 13:57 Hello all, pretty new to Project so I appreciate the help on remedial concepts. Project 2k3 I have: hours per day: 8 hours per week: 40 days per month: 20 First, the Duration column converts groupings of hours to portions of days. I would like to only display the items in terms of hours. Second, kind of a side note... I have the following lines items: Line item 1 - .38 days sub a - 3 hrs sub b - 3 hrs how is 6 hours out of 8 an hour work day .38 days? Also, I have: Master line item 1.25 days sub 1 - 2 hrs sub 2 - 1.25 days sub 2.a - x sub 2.b - y sub 3 - .38 days sub 3.a - 3 hrs sub 3.b - 3 hrs I truly have no idea how that works. To get the master line item duration I would expect the total to be the summation of all its child nodes' durations, which in turn is the recursive summation of all its child nodes. How does 1.25 days = 2 hours + 1.25 days + .38 days? Thanks again for your help in this matter, I am probably just missing how this works.
From: "JulieS" <passport6847 at maine dot rr dot on 11 Nov 2005 14:54 Hi BurnChrome, My answers are in-line with your questions. Hope this helps. Let us know how you get along. Julie "BurnChrome" <BurnChrome(a)discussions.microsoft.com> wrote in message news:4975F503-F1AA-4DE7-A49B-3C0624A54862(a)microsoft.com... > Hello all, pretty new to Project so I appreciate the help on remedial > concepts. > > Project 2k3 > > I have: > hours per day: 8 > hours per week: 40 > days per month: 20 > > First, the Duration column converts groupings of hours to portions of > days. > I would like to only display the items in terms of hours. Run the Format_Duration macro. Tools >Macros >Macro... Format Duration Select hours from the drop-down. Click Run. > > Second, kind of a side note... I have the following lines items: > > Line item 1 - .38 days > sub a - 3 hrs > sub b - 3 hrs > > how is 6 hours out of 8 an hour work day .38 days? If sub a & sub b tasks are not linked, then the duration of the summary task is not the sum of the durations of the subtasks. The duration of a summary tasks is the amount of time (in working time from the start of the earliest sub task to the finish of the latest subtask. So 3 hours out of an 8 hour day is .38 - actual .375. > > Also, I have: > > Master line item 1.25 days > sub 1 - 2 hrs > sub 2 - 1.25 days > sub 2.a - x > sub 2.b - y > sub 3 - .38 days > sub 3.a - 3 hrs > sub 3.b - 3 hrs > > I truly have no idea how that works. To get the master line item duration > I > would expect the total to be the summation of all its child nodes' > durations, > which in turn is the recursive summation of all its child nodes. > > How does 1.25 days = 2 hours + 1.25 days + .38 days? > > Thanks again for your help in this matter, I am probably just missing how > this works. > >
From: Mike Glen on 11 Nov 2005 15:09 Hi BurnChrome, Welcome to this Microsoft Project newsgroup :) You might like to have a look at my series on Microsoft Project in the TechTrax ezine at this site: http://tinyurl.com/2xbhc or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 (Perhaps you'd care to rate the articles before leaving the site, :) Thanks.) FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/> Hope this helps - please let us know how you get on :) Mike Glen MS Project MVP JulieS wrote: > Hi BurnChrome, > > My answers are in-line with your questions. > > Hope this helps. Let us know how you get along. > > Julie > > "BurnChrome" <BurnChrome(a)discussions.microsoft.com> wrote in message > news:4975F503-F1AA-4DE7-A49B-3C0624A54862(a)microsoft.com... >> Hello all, pretty new to Project so I appreciate the help on remedial >> concepts. >> >> Project 2k3 >> >> I have: >> hours per day: 8 >> hours per week: 40 >> days per month: 20 >> >> First, the Duration column converts groupings of hours to portions of >> days. >> I would like to only display the items in terms of hours. > > Run the Format_Duration macro. Tools >Macros >Macro... > Format Duration > Select hours from the drop-down. > Click Run. >> >> Second, kind of a side note... I have the following lines items: >> >> Line item 1 - .38 days >> sub a - 3 hrs >> sub b - 3 hrs >> >> how is 6 hours out of 8 an hour work day .38 days? > If sub a & sub b tasks are not linked, then the duration of the > summary task is not the sum of the durations of the subtasks. The > duration of a summary tasks is the amount of time (in working time > from the start of the earliest sub task to the finish of the latest > subtask. So 3 hours out of an 8 hour day is .38 - actual .375. > >> >> Also, I have: >> >> Master line item 1.25 days >> sub 1 - 2 hrs >> sub 2 - 1.25 days >> sub 2.a - x >> sub 2.b - y >> sub 3 - .38 days >> sub 3.a - 3 hrs >> sub 3.b - 3 hrs >> >> I truly have no idea how that works. To get the master line item >> duration I >> would expect the total to be the summation of all its child nodes' >> durations, >> which in turn is the recursive summation of all its child nodes. >> >> How does 1.25 days = 2 hours + 1.25 days + .38 days? >> >> Thanks again for your help in this matter, I am probably just >> missing how this works.
From: BurnChrome on 11 Nov 2005 16:01 Sweet thanks JulieS, I found the macro, looking good now. Now I get how the duration works. If I have two sub items, 1 hrs and 2hrs, the parent line item is going to be 2 hrs because they both start at the same time and the parent takes the start and end date of the items and gets 2 hrs, not 3 hrs. So my question would be how to associate the sub items in a way so the parent line item's duration is not based on the start and end time, but the summation of the durations. So basically the units of work are not dependent on each other chronologically, a user complete the items anytime they like and update the line items actual start date and actual end date. Thanks a bunch for the help. I can't wait to get the basics of Project down so I can use it in the Foundation Server I have setup.
From: "JulieS" <passport6847 at maine dot rr dot on 11 Nov 2005 16:17 Hi, Glad to know the guidance thus far has been helpful and thanks for the feedback. Your description of summary task duration is correct. I am guess that you are actually more interested in *work* at the summary task level than duration. If, as you describe, the tasks are not dependent upon one another and can both start at the same time, then linking the tasks finish to start to force summary duration to be the sum of the subtask durations not suit what you need. If you have assigned resources to the tasks, you can add the work column (field). The work field for a summary tasks is the sum of the work for the subtasks. As your users update the project with actual work, the summary tasks will have both scheduled work (as long as you have baselined) and actual work for the subtasks. Hope this helps. Please let us know if you have further questions. Julie
|
Next
|
Last
Pages: 1 2 Prev: Problem starting up Project 2000 - runtime error Next: Fail to download control |