From: Sherri on
Hi there,

I'm hoping there's an easy solution to this problem...all of my project
schedules appear to have the same issue.

The problem: fixed duration tasks are increasing their duration when
changes are made to (seemingly) unrelated tasks.

Example: Task A has a duration of 10 days. MS project has changed the
duration to 12.38 days. When the duration is reduced back to 10 days, a
warning message appears saying that Task X has had its duration increased to
accomodate the change made to Task A. When I investigate what has happened to
Task X, usually the duration has increased (quite significantly), say from 10
days to 26 days. When Task X is returned to its 10 day duration, the same
warning message appears for a different task, and so the domino effect goes
through the project until I've exhausted all of the tasks.

As far as I can tell, none of these tasks are directly related to one
another and there is no logical reason for a change in duration of one task
to affect the duration of another.

To add to the misery, it doesn't always warn me that it's changing a
duration elsewhere in the project.

help - it's wreaking havoc on my completion dates.

Thanks. Sherri


From: "Jan De Messemaeker" jandemes at prom hyphen ade dot on
Just a hunch... do you have automatic leveling on?

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Sherri" <Sherri(a)discussions.microsoft.com> schreef in bericht
news:4D2C4623-D3A3-4693-9D04-ABE61186C431(a)microsoft.com...
> Hi there,
>
> I'm hoping there's an easy solution to this problem...all of my project
> schedules appear to have the same issue.
>
> The problem: fixed duration tasks are increasing their duration when
> changes are made to (seemingly) unrelated tasks.
>
> Example: Task A has a duration of 10 days. MS project has changed the
> duration to 12.38 days. When the duration is reduced back to 10 days, a
> warning message appears saying that Task X has had its duration increased
to
> accomodate the change made to Task A. When I investigate what has happened
to
> Task X, usually the duration has increased (quite significantly), say from
10
> days to 26 days. When Task X is returned to its 10 day duration, the same
> warning message appears for a different task, and so the domino effect
goes
> through the project until I've exhausted all of the tasks.
>
> As far as I can tell, none of these tasks are directly related to one
> another and there is no logical reason for a change in duration of one
task
> to affect the duration of another.
>
> To add to the misery, it doesn't always warn me that it's changing a
> duration elsewhere in the project.
>
> help - it's wreaking havoc on my completion dates.
>
> Thanks. Sherri
>
>


From: Sherri on
Oooh...I wish it were that :)

Leveling is set to Manual.

Sherri

"Jan De Messemaeker" wrote:

> Just a hunch... do you have automatic leveling on?
>
> --
> Jan De Messemaeker, Microsoft Project Most Valuable Professional
> http://users.online.be/prom-ade/
> For FAQs: http://www.mvps.org/project/faqs.htm
> "Sherri" <Sherri(a)discussions.microsoft.com> schreef in bericht
> news:4D2C4623-D3A3-4693-9D04-ABE61186C431(a)microsoft.com...
> > Hi there,
> >
> > I'm hoping there's an easy solution to this problem...all of my project
> > schedules appear to have the same issue.
> >
> > The problem: fixed duration tasks are increasing their duration when
> > changes are made to (seemingly) unrelated tasks.
> >
> > Example: Task A has a duration of 10 days. MS project has changed the
> > duration to 12.38 days. When the duration is reduced back to 10 days, a
> > warning message appears saying that Task X has had its duration increased
> to
> > accomodate the change made to Task A. When I investigate what has happened
> to
> > Task X, usually the duration has increased (quite significantly), say from
> 10
> > days to 26 days. When Task X is returned to its 10 day duration, the same
> > warning message appears for a different task, and so the domino effect
> goes
> > through the project until I've exhausted all of the tasks.
> >
> > As far as I can tell, none of these tasks are directly related to one
> > another and there is no logical reason for a change in duration of one
> task
> > to affect the duration of another.
> >
> > To add to the misery, it doesn't always warn me that it's changing a
> > duration elsewhere in the project.
> >
> > help - it's wreaking havoc on my completion dates.
> >
> > Thanks. Sherri
> >
> >
>
>
>
From: "JulieS" passport6847 at maine dot rr dot on
Hi Sherri,

It may be an issue related to non-working time for resources. Project
will change the duration of a fixed duration task to accommodate a
change in resource calendars. If you are changing durations of Task X
and it is linked to Task A, if Task A now falls into non-working time
for a resource, the duration will change.

I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

"Sherri" <Sherri(a)discussions.microsoft.com> wrote in message
news:9C17D1CC-7EC9-4805-A5A2-4149D9BE34DE(a)microsoft.com...
> Oooh...I wish it were that :)
>
> Leveling is set to Manual.
>
> Sherri
>
> "Jan De Messemaeker" wrote:
>
>> Just a hunch... do you have automatic leveling on?
>>
>> --
>> Jan De Messemaeker, Microsoft Project Most Valuable Professional
>> http://users.online.be/prom-ade/
>> For FAQs: http://www.mvps.org/project/faqs.htm
>> "Sherri" <Sherri(a)discussions.microsoft.com> schreef in bericht
>> news:4D2C4623-D3A3-4693-9D04-ABE61186C431(a)microsoft.com...
>> > Hi there,
>> >
>> > I'm hoping there's an easy solution to this problem...all of my
>> > project
>> > schedules appear to have the same issue.
>> >
>> > The problem: fixed duration tasks are increasing their duration
>> > when
>> > changes are made to (seemingly) unrelated tasks.
>> >
>> > Example: Task A has a duration of 10 days. MS project has changed
>> > the
>> > duration to 12.38 days. When the duration is reduced back to 10
>> > days, a
>> > warning message appears saying that Task X has had its duration
>> > increased
>> to
>> > accomodate the change made to Task A. When I investigate what has
>> > happened
>> to
>> > Task X, usually the duration has increased (quite significantly),
>> > say from
>> 10
>> > days to 26 days. When Task X is returned to its 10 day duration,
>> > the same
>> > warning message appears for a different task, and so the domino
>> > effect
>> goes
>> > through the project until I've exhausted all of the tasks.
>> >
>> > As far as I can tell, none of these tasks are directly related to
>> > one
>> > another and there is no logical reason for a change in duration of
>> > one
>> task
>> > to affect the duration of another.
>> >
>> > To add to the misery, it doesn't always warn me that it's changing
>> > a
>> > duration elsewhere in the project.
>> >
>> > help - it's wreaking havoc on my completion dates.
>> >
>> > Thanks. Sherri
>> >
>> >
>>
>>
>>


From: Sherri on
Thanks Julie,

That's definitely part of it, the resource works a 4-day week, with 5 weeks
on and 1 week off. The calendar has been set to reflect that, but the
durations still exceed the length of time that should be scheduled even with
the non-working time factored in. For example, the duration of a task A is 6
days long, but there are 4 non-working days that fall within that time, which
should make the duration 10 days. The problem is that the duration is being
set much higher, say 17 days.


"JulieS" wrote:

> Hi Sherri,
>
> It may be an issue related to non-working time for resources. Project
> will change the duration of a fixed duration task to accommodate a
> change in resource calendars. If you are changing durations of Task X
> and it is linked to Task A, if Task A now falls into non-working time
> for a resource, the duration will change.
>
> I hope this helps. Let us know how you get along.
>
> Julie
>
> Visit http://project.mvps.org/ for FAQs and more information about
> Microsoft Project.
>
> "Sherri" <Sherri(a)discussions.microsoft.com> wrote in message
> news:9C17D1CC-7EC9-4805-A5A2-4149D9BE34DE(a)microsoft.com...
> > Oooh...I wish it were that :)
> >
> > Leveling is set to Manual.
> >
> > Sherri
> >
> > "Jan De Messemaeker" wrote:
> >
> >> Just a hunch... do you have automatic leveling on?
> >>
> >> --
> >> Jan De Messemaeker, Microsoft Project Most Valuable Professional
> >> http://users.online.be/prom-ade/
> >> For FAQs: http://www.mvps.org/project/faqs.htm
> >> "Sherri" <Sherri(a)discussions.microsoft.com> schreef in bericht
> >> news:4D2C4623-D3A3-4693-9D04-ABE61186C431(a)microsoft.com...
> >> > Hi there,
> >> >
> >> > I'm hoping there's an easy solution to this problem...all of my
> >> > project
> >> > schedules appear to have the same issue.
> >> >
> >> > The problem: fixed duration tasks are increasing their duration
> >> > when
> >> > changes are made to (seemingly) unrelated tasks.
> >> >
> >> > Example: Task A has a duration of 10 days. MS project has changed
> >> > the
> >> > duration to 12.38 days. When the duration is reduced back to 10
> >> > days, a
> >> > warning message appears saying that Task X has had its duration
> >> > increased
> >> to
> >> > accomodate the change made to Task A. When I investigate what has
> >> > happened
> >> to
> >> > Task X, usually the duration has increased (quite significantly),
> >> > say from
> >> 10
> >> > days to 26 days. When Task X is returned to its 10 day duration,
> >> > the same
> >> > warning message appears for a different task, and so the domino
> >> > effect
> >> goes
> >> > through the project until I've exhausted all of the tasks.
> >> >
> >> > As far as I can tell, none of these tasks are directly related to
> >> > one
> >> > another and there is no logical reason for a change in duration of
> >> > one
> >> task
> >> > to affect the duration of another.
> >> >
> >> > To add to the misery, it doesn't always warn me that it's changing
> >> > a
> >> > duration elsewhere in the project.
> >> >
> >> > help - it's wreaking havoc on my completion dates.
> >> >
> >> > Thanks. Sherri
> >> >
> >> >
> >>
> >>
> >>
>
>
>