|
From: Sherri on 3 Aug 2006 13:51 Hi there, I'm hoping there's an easy solution to this problem...all of my project schedules appear to have the same issue. The problem: fixed duration tasks are increasing their duration when changes are made to (seemingly) unrelated tasks. Example: Task A has a duration of 10 days. MS project has changed the duration to 12.38 days. When the duration is reduced back to 10 days, a warning message appears saying that Task X has had its duration increased to accomodate the change made to Task A. When I investigate what has happened to Task X, usually the duration has increased (quite significantly), say from 10 days to 26 days. When Task X is returned to its 10 day duration, the same warning message appears for a different task, and so the domino effect goes through the project until I've exhausted all of the tasks. As far as I can tell, none of these tasks are directly related to one another and there is no logical reason for a change in duration of one task to affect the duration of another. To add to the misery, it doesn't always warn me that it's changing a duration elsewhere in the project. help - it's wreaking havoc on my completion dates. Thanks. Sherri
From: "Jan De Messemaeker" jandemes at prom hyphen ade dot on 3 Aug 2006 14:12 Just a hunch... do you have automatic leveling on? -- Jan De Messemaeker, Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ For FAQs: http://www.mvps.org/project/faqs.htm "Sherri" <Sherri(a)discussions.microsoft.com> schreef in bericht news:4D2C4623-D3A3-4693-9D04-ABE61186C431(a)microsoft.com... > Hi there, > > I'm hoping there's an easy solution to this problem...all of my project > schedules appear to have the same issue. > > The problem: fixed duration tasks are increasing their duration when > changes are made to (seemingly) unrelated tasks. > > Example: Task A has a duration of 10 days. MS project has changed the > duration to 12.38 days. When the duration is reduced back to 10 days, a > warning message appears saying that Task X has had its duration increased to > accomodate the change made to Task A. When I investigate what has happened to > Task X, usually the duration has increased (quite significantly), say from 10 > days to 26 days. When Task X is returned to its 10 day duration, the same > warning message appears for a different task, and so the domino effect goes > through the project until I've exhausted all of the tasks. > > As far as I can tell, none of these tasks are directly related to one > another and there is no logical reason for a change in duration of one task > to affect the duration of another. > > To add to the misery, it doesn't always warn me that it's changing a > duration elsewhere in the project. > > help - it's wreaking havoc on my completion dates. > > Thanks. Sherri > >
From: Sherri on 3 Aug 2006 14:36 Oooh...I wish it were that :) Leveling is set to Manual. Sherri "Jan De Messemaeker" wrote: > Just a hunch... do you have automatic leveling on? > > -- > Jan De Messemaeker, Microsoft Project Most Valuable Professional > http://users.online.be/prom-ade/ > For FAQs: http://www.mvps.org/project/faqs.htm > "Sherri" <Sherri(a)discussions.microsoft.com> schreef in bericht > news:4D2C4623-D3A3-4693-9D04-ABE61186C431(a)microsoft.com... > > Hi there, > > > > I'm hoping there's an easy solution to this problem...all of my project > > schedules appear to have the same issue. > > > > The problem: fixed duration tasks are increasing their duration when > > changes are made to (seemingly) unrelated tasks. > > > > Example: Task A has a duration of 10 days. MS project has changed the > > duration to 12.38 days. When the duration is reduced back to 10 days, a > > warning message appears saying that Task X has had its duration increased > to > > accomodate the change made to Task A. When I investigate what has happened > to > > Task X, usually the duration has increased (quite significantly), say from > 10 > > days to 26 days. When Task X is returned to its 10 day duration, the same > > warning message appears for a different task, and so the domino effect > goes > > through the project until I've exhausted all of the tasks. > > > > As far as I can tell, none of these tasks are directly related to one > > another and there is no logical reason for a change in duration of one > task > > to affect the duration of another. > > > > To add to the misery, it doesn't always warn me that it's changing a > > duration elsewhere in the project. > > > > help - it's wreaking havoc on my completion dates. > > > > Thanks. Sherri > > > > > > >
From: "JulieS" passport6847 at maine dot rr dot on 3 Aug 2006 15:09 Hi Sherri, It may be an issue related to non-working time for resources. Project will change the duration of a fixed duration task to accommodate a change in resource calendars. If you are changing durations of Task X and it is linked to Task A, if Task A now falls into non-working time for a resource, the duration will change. I hope this helps. Let us know how you get along. Julie Visit http://project.mvps.org/ for FAQs and more information about Microsoft Project. "Sherri" <Sherri(a)discussions.microsoft.com> wrote in message news:9C17D1CC-7EC9-4805-A5A2-4149D9BE34DE(a)microsoft.com... > Oooh...I wish it were that :) > > Leveling is set to Manual. > > Sherri > > "Jan De Messemaeker" wrote: > >> Just a hunch... do you have automatic leveling on? >> >> -- >> Jan De Messemaeker, Microsoft Project Most Valuable Professional >> http://users.online.be/prom-ade/ >> For FAQs: http://www.mvps.org/project/faqs.htm >> "Sherri" <Sherri(a)discussions.microsoft.com> schreef in bericht >> news:4D2C4623-D3A3-4693-9D04-ABE61186C431(a)microsoft.com... >> > Hi there, >> > >> > I'm hoping there's an easy solution to this problem...all of my >> > project >> > schedules appear to have the same issue. >> > >> > The problem: fixed duration tasks are increasing their duration >> > when >> > changes are made to (seemingly) unrelated tasks. >> > >> > Example: Task A has a duration of 10 days. MS project has changed >> > the >> > duration to 12.38 days. When the duration is reduced back to 10 >> > days, a >> > warning message appears saying that Task X has had its duration >> > increased >> to >> > accomodate the change made to Task A. When I investigate what has >> > happened >> to >> > Task X, usually the duration has increased (quite significantly), >> > say from >> 10 >> > days to 26 days. When Task X is returned to its 10 day duration, >> > the same >> > warning message appears for a different task, and so the domino >> > effect >> goes >> > through the project until I've exhausted all of the tasks. >> > >> > As far as I can tell, none of these tasks are directly related to >> > one >> > another and there is no logical reason for a change in duration of >> > one >> task >> > to affect the duration of another. >> > >> > To add to the misery, it doesn't always warn me that it's changing >> > a >> > duration elsewhere in the project. >> > >> > help - it's wreaking havoc on my completion dates. >> > >> > Thanks. Sherri >> > >> > >> >> >>
From: Sherri on 3 Aug 2006 15:31
Thanks Julie, That's definitely part of it, the resource works a 4-day week, with 5 weeks on and 1 week off. The calendar has been set to reflect that, but the durations still exceed the length of time that should be scheduled even with the non-working time factored in. For example, the duration of a task A is 6 days long, but there are 4 non-working days that fall within that time, which should make the duration 10 days. The problem is that the duration is being set much higher, say 17 days. "JulieS" wrote: > Hi Sherri, > > It may be an issue related to non-working time for resources. Project > will change the duration of a fixed duration task to accommodate a > change in resource calendars. If you are changing durations of Task X > and it is linked to Task A, if Task A now falls into non-working time > for a resource, the duration will change. > > I hope this helps. Let us know how you get along. > > Julie > > Visit http://project.mvps.org/ for FAQs and more information about > Microsoft Project. > > "Sherri" <Sherri(a)discussions.microsoft.com> wrote in message > news:9C17D1CC-7EC9-4805-A5A2-4149D9BE34DE(a)microsoft.com... > > Oooh...I wish it were that :) > > > > Leveling is set to Manual. > > > > Sherri > > > > "Jan De Messemaeker" wrote: > > > >> Just a hunch... do you have automatic leveling on? > >> > >> -- > >> Jan De Messemaeker, Microsoft Project Most Valuable Professional > >> http://users.online.be/prom-ade/ > >> For FAQs: http://www.mvps.org/project/faqs.htm > >> "Sherri" <Sherri(a)discussions.microsoft.com> schreef in bericht > >> news:4D2C4623-D3A3-4693-9D04-ABE61186C431(a)microsoft.com... > >> > Hi there, > >> > > >> > I'm hoping there's an easy solution to this problem...all of my > >> > project > >> > schedules appear to have the same issue. > >> > > >> > The problem: fixed duration tasks are increasing their duration > >> > when > >> > changes are made to (seemingly) unrelated tasks. > >> > > >> > Example: Task A has a duration of 10 days. MS project has changed > >> > the > >> > duration to 12.38 days. When the duration is reduced back to 10 > >> > days, a > >> > warning message appears saying that Task X has had its duration > >> > increased > >> to > >> > accomodate the change made to Task A. When I investigate what has > >> > happened > >> to > >> > Task X, usually the duration has increased (quite significantly), > >> > say from > >> 10 > >> > days to 26 days. When Task X is returned to its 10 day duration, > >> > the same > >> > warning message appears for a different task, and so the domino > >> > effect > >> goes > >> > through the project until I've exhausted all of the tasks. > >> > > >> > As far as I can tell, none of these tasks are directly related to > >> > one > >> > another and there is no logical reason for a change in duration of > >> > one > >> task > >> > to affect the duration of another. > >> > > >> > To add to the misery, it doesn't always warn me that it's changing > >> > a > >> > duration elsewhere in the project. > >> > > >> > help - it's wreaking havoc on my completion dates. > >> > > >> > Thanks. Sherri > >> > > >> > > >> > >> > >> > > > |