From: Pete Smith on
Hi,

is it possible configure Project to use the 50/50 Technique for EVA?

Thanks in advance
Pete

--
Pete Smith


From: John on
In article <eMtVdXUDGHA.208(a)tk2msftngp13.phx.gbl>,
"Pete Smith" <msdn(a)nospam.com> wrote:

> Hi,
>
> is it possible configure Project to use the 50/50 Technique for EVA?
>
> Thanks in advance
> Pete

Pete,
Sure, it's really a matter of how progress is reported. If value is
"taken" only as 50% and 100% (or other common values such as 25/75.
60/40, etc.), then the EV data will be what you want.

John
Project MVP
From: davegb on

John wrote:
> In article <eMtVdXUDGHA.208(a)tk2msftngp13.phx.gbl>,
> "Pete Smith" <msdn(a)nospam.com> wrote:
>
> > Hi,
> >
> > is it possible configure Project to use the 50/50 Technique for EVA?
> >
> > Thanks in advance
> > Pete
>
> Pete,
> Sure, it's really a matter of how progress is reported. If value is
> "taken" only as 50% and 100% (or other common values such as 25/75.
> 60/40, etc.), then the EV data will be what you want.
>
> John
> Project MVP

I think it will work as long as your durations are relatively short. If
you have long duration tasks relative to the duration of your project,
then you will have unreported value being earned, but actual expenses
acruing, throwing off your EV.

From: John on
In article <1135961912.983774.108570(a)f14g2000cwb.googlegroups.com>,
"davegb" <davegb(a)safebrowse.com> wrote:

> John wrote:
> > In article <eMtVdXUDGHA.208(a)tk2msftngp13.phx.gbl>,
> > "Pete Smith" <msdn(a)nospam.com> wrote:
> >
> > > Hi,
> > >
> > > is it possible configure Project to use the 50/50 Technique for EVA?
> > >
> > > Thanks in advance
> > > Pete
> >
> > Pete,
> > Sure, it's really a matter of how progress is reported. If value is
> > "taken" only as 50% and 100% (or other common values such as 25/75.
> > 60/40, etc.), then the EV data will be what you want.
> >
> > John
> > Project MVP
>
> I think it will work as long as your durations are relatively short. If
> you have long duration tasks relative to the duration of your project,
> then you will have unreported value being earned, but actual expenses
> acruing, throwing off your EV.

Dave,
It depends on what you mean by "relatively short". In our case any tasks
that were greater than one month but less than three months (yeah that's
something like two isn't it), could have a 50/50, 25/75, or 40/60 earned
value method (we used monthly statusing/reporting). And yes, such
discrete EV methods do throw a skew into the overall data but it
balances out. I might add that this method is used and preferred on many
Government contracts.

John
From: Trevor Rabey on
The more Tasks that you create, and the shorter their durations, the more
control and accuracy you obtain and the less you need to be concerned about
monitoring and reporting fractions of task completion.
You could settle on "no finer level of progress reporting than 50%
completion" but if you make enough tasks which are indivually short enough
you can happily adopt "no finer level of progress reporting than 100%
completion" without acquiring too much over/under reporting error in a given
period. What doesn't get picked up this month will get picked up next month
(or next week).
See the Tracking Toolbar. It is already set for 0, 25%, 50%, 75%, 100%.


"Pete Smith" <msdn(a)nospam.com> wrote in message
news:eMtVdXUDGHA.208(a)tk2msftngp13.phx.gbl...
> Hi,
>
> is it possible configure Project to use the 50/50 Technique for EVA?
>
> Thanks in advance
> Pete
>
> --
> Pete Smith
>


 |  Next  |  Last
Pages: 1 2
Prev: what is a baseline?
Next: How to define continuous task