From: BlaiseR on 22 Apr 2008 09:42 I have Fixed Units tasks (not Effort Driven) and the Options "Move end of completed parts after status date back to status date" and "Move start of remaining parts before status date forward to status date" and "Split in-progress tasks" set. When I update a task status by increasing the "% Complete" manually, tasks split as expected, pushing the remaining work in a task to start at the Status Date (or Current Date, if Status Date is not set). However, if I go into the Task Usage view and enter Actual Hours for that same task, the "% Complete" updates, but the task DOES NOT split, and leave remaining work in the past, before the status date. This does not seem right. Am I missing a setting somewhere? -- Thanks.
From: JulieS on 24 Apr 2008 18:17 Hello BlaiseR, No, you're not missing a setting. As you note, incomplete work is only shifted when you update using % complete or enter actual work in a non-time phased view (neither Task nor Resource Usage). If you want to use the timephased view, use the "Reschedule uncompleted work" command in the Tools > Tracking > Update Project dialog to shift any incomplete work to the status date. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "BlaiseR" <BlaiseR(a)discussions.microsoft.com> wrote in message news:98E97FF1-7789-4456-8CDA-B8A204973180(a)microsoft.com... >I have Fixed Units tasks (not Effort Driven) and the Options "Move >end of > completed parts after status date back to status date" and "Move > start of > remaining parts before status date forward to status date" and > "Split > in-progress tasks" set. When I update a task status by increasing > the "% > Complete" manually, tasks split as expected, pushing the remaining > work in a > task to start at the Status Date (or Current Date, if Status Date is > not > set). However, if I go into the Task Usage view and enter Actual > Hours for > that same task, the "% Complete" updates, but the task DOES NOT > split, and > leave remaining work in the past, before the status date. This does > not seem > right. Am I missing a setting somewhere? > -- > Thanks.
|
Pages: 1 Prev: Merged projects resource graph?? Next: Is it possible to hightlight a row in Project like in Excel? |