From: BlaiseR on
JulieS - Thanks! That did the trick. You are a lifesaver. - BlaiseR
--
Thanks.


"JulieS" wrote:

> Hello BlaiseR,
>
> No, you're not missing a setting. As you note, incomplete work is
> only shifted when you update using % complete or enter actual work in
> a non-time phased view (neither Task nor Resource Usage).
>
> If you want to use the timephased view, use the "Reschedule
> uncompleted work" command in the Tools > Tracking > Update Project
> dialog to shift any incomplete work to the status date.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
>
> "BlaiseR" <BlaiseR(a)discussions.microsoft.com> wrote in message
> news:98E97FF1-7789-4456-8CDA-B8A204973180(a)microsoft.com...
> >I have Fixed Units tasks (not Effort Driven) and the Options "Move
> >end of
> > completed parts after status date back to status date" and "Move
> > start of
> > remaining parts before status date forward to status date" and
> > "Split
> > in-progress tasks" set. When I update a task status by increasing
> > the "%
> > Complete" manually, tasks split as expected, pushing the remaining
> > work in a
> > task to start at the Status Date (or Current Date, if Status Date is
> > not
> > set). However, if I go into the Task Usage view and enter Actual
> > Hours for
> > that same task, the "% Complete" updates, but the task DOES NOT
> > split, and
> > leave remaining work in the past, before the status date. This does
> > not seem
> > right. Am I missing a setting somewhere?
> > --
> > Thanks.
>
>
>
From: JulieS on
You're most welcome BlaiseR and thanks for the feedback.
Julie
"BlaiseR" <BlaiseR(a)discussions.microsoft.com> wrote in message
news:9AB97C81-611C-4ED7-877F-418151956382(a)microsoft.com...
> JulieS - Thanks! That did the trick. You are a lifesaver. -
> BlaiseR
> --
> Thanks.
>
>
> "JulieS" wrote:
>
>> Hello BlaiseR,
>>
>> No, you're not missing a setting. As you note, incomplete work is
>> only shifted when you update using % complete or enter actual work
>> in
>> a non-time phased view (neither Task nor Resource Usage).
>>
>> If you want to use the timephased view, use the "Reschedule
>> uncompleted work" command in the Tools > Tracking > Update Project
>> dialog to shift any incomplete work to the status date.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information
>> about Microsoft Project
>>
>>
>> "BlaiseR" <BlaiseR(a)discussions.microsoft.com> wrote in message
>> news:98E97FF1-7789-4456-8CDA-B8A204973180(a)microsoft.com...
>> >I have Fixed Units tasks (not Effort Driven) and the Options "Move
>> >end of
>> > completed parts after status date back to status date" and "Move
>> > start of
>> > remaining parts before status date forward to status date" and
>> > "Split
>> > in-progress tasks" set. When I update a task status by
>> > increasing
>> > the "%
>> > Complete" manually, tasks split as expected, pushing the
>> > remaining
>> > work in a
>> > task to start at the Status Date (or Current Date, if Status Date
>> > is
>> > not
>> > set). However, if I go into the Task Usage view and enter Actual
>> > Hours for
>> > that same task, the "% Complete" updates, but the task DOES NOT
>> > split, and
>> > leave remaining work in the past, before the status date. This
>> > does
>> > not seem
>> > right. Am I missing a setting somewhere?
>> > --
>> > Thanks.
>>
>>
>>