From: CB on 28 Apr 2008 11:45 Is there a simple way to export the unassigned task for a project to excel? I am using 2007 standard and only need to export task for a single project that have no resource assignment. I would like to include the duration and start and finish fields. Any ideas greatly appreciated.
From: Rod Gill on 28 Apr 2008 16:59 Hi, Try creating a filter that shows all tasks with Resource Names=Blank then File, Save as and select Excel .xls format. A wizard will then start and you can select which fields you want exported by creating your own map. -- Rod Gill Microsoft MVP for Project Author of the only book on Project VBA, see: http://www.projectvbabook.com "CB" <CB(a)dsucussions.microsoft.com> wrote in message news:42EB753B-9F69-4E36-9FF8-63B7735AF3EB(a)microsoft.com... > Is there a simple way to export the unassigned task for a project to > excel? > I am using 2007 standard and only need to export task for a single project > that have no resource assignment. I would like to include the duration > and > start and finish fields. Any ideas greatly appreciated.
|
Pages: 1 Prev: Microsoft Project EPM problem Next: Automatically removing completed projects from Master |