|
Prev: How can I copy my Auto correct file to another computer
Next: Link Project data into Excel Worksheet
From: Michelle on 9 Feb 2006 17:21 Hello, I am trying to create colums within the task sheet to reflect Estimated Hours of work to complete a task, Actual Hours it took to complete the task (where the variance would be hours that the resource now has free, or hours that must be taken from another task, depending on the variance). In other words, I scheduled a task to take 5 hours. It actually took 6, so I need to reflect the 1 hour variance of extra time it took to complete this task. Conversely, if it actually took 4 hours, I now have 1 "free" hour that was not used for this project. The remaining work function and % of work complete seems to calculate the variance as the hours remaining to be worked in order to complete the task. Thanks!
From: "Rod Gill" <rod AT project-systems DOT co DOT on 9 Feb 2006 17:33
Try inserting the Work Variance column. It requires you to have saved a baseline (Tools, Tracking, Save Baseline) to work. -- Rod Gill Project MVP Visit www.msproject-systems.com for Project Companion Tools and more "Michelle" <Michelle(a)discussions.microsoft.com> wrote in message news:84920A86-E0C4-49B3-A669-8AA3E57B2066(a)microsoft.com... > Hello, > I am trying to create colums within the task sheet to reflect Estimated > Hours of work to complete a task, Actual Hours it took to complete the > task > (where the variance would be hours that the resource now has free, or > hours > that must be taken from another task, depending on the variance). In > other > words, I scheduled a task to take 5 hours. It actually took 6, so I need > to > reflect the 1 hour variance of extra time it took to complete this task. > Conversely, if it actually took 4 hours, I now have 1 "free" hour that was > not used for this project. > > The remaining work function and % of work complete seems to calculate the > variance as the hours remaining to be worked in order to complete the > task. > > Thanks! |