From: Mike Frenette on
I recently changed the height of a task in an MS Project plan so it would
wrap the task name in a view of a Gantt chart. For some reason, the grey
block to the left of all tasks became clear, and I am no longer able to
select a task to make it regular height again.

Suggestions as to why this might have occurred?

Thanks,
Mike
From: Jim Spiller on
Either the first column is no longer locked or it is hidden (0 width). Go to
View-Table-More Tables and click Edit to give the first some a width greater
than 0 or Lock it. Click Apply after clicking OK to these changes...


"Mike Frenette" <MikeFrenette(a)discussions.microsoft.com> wrote in message
news:4D42F47A-A27C-4994-8186-59CA1C9360C7(a)microsoft.com...
>I recently changed the height of a task in an MS Project plan so it would
> wrap the task name in a view of a Gantt chart. For some reason, the grey
> block to the left of all tasks became clear, and I am no longer able to
> select a task to make it regular height again.
>
> Suggestions as to why this might have occurred?
>
> Thanks,
> Mike