From: cavegirl13 on 5 Feb 2006 12:53 Does anyone know how I can insert a new column in a Gantt chart in MS Project 2003 that will enable me to show 'Red, Amber' Green' status of the tasks?
From: "JulieS" <passport6847 at maine dot rr dot on 5 Feb 2006 13:12 Hi cavegirl13, Take a look at Mike Glen's excellent series of articles about MS Project at: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 particularly Articles 14 & 15. You may also try searching this newsgroup for "RAG". I hope this helps. Let us know how you get along. Julie "cavegirl13" <cavegirl13(a)discussions.microsoft.com> wrote in message news:7A826D5B-9241-4AD8-B165-ED61F80500B2(a)microsoft.com... > Does anyone know how I can insert a new column in a Gantt chart in MS > Project > 2003 that will enable me to show 'Red, Amber' Green' status of the tasks?
From: cavegirl13 on 8 Feb 2006 04:40 Great thank you :-) "JulieS" wrote: > Hi cavegirl13, > > Take a look at Mike Glen's excellent series of articles about MS Project at: > http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 > > particularly Articles 14 & 15. > > You may also try searching this newsgroup for "RAG". > > I hope this helps. Let us know how you get along. > > Julie > "cavegirl13" <cavegirl13(a)discussions.microsoft.com> wrote in message > news:7A826D5B-9241-4AD8-B165-ED61F80500B2(a)microsoft.com... > > Does anyone know how I can insert a new column in a Gantt chart in MS > > Project > > 2003 that will enable me to show 'Red, Amber' Green' status of the tasks? > > >
From: "JulieS" <passport6847 at maine dot rr dot on 8 Feb 2006 07:04 You're welcome cavegirl13 and thanks for the feedback. Julie "cavegirl13" <cavegirl13(a)discussions.microsoft.com> wrote in message news:E1952E8B-6C8D-48CE-A309-91C50CD92FA1(a)microsoft.com... > Great thank you :-) > > "JulieS" wrote: > >> Hi cavegirl13, >> >> Take a look at Mike Glen's excellent series of articles about MS Project >> at: >> http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 >> >> particularly Articles 14 & 15. >> >> You may also try searching this newsgroup for "RAG". >> >> I hope this helps. Let us know how you get along. >> >> Julie >> "cavegirl13" <cavegirl13(a)discussions.microsoft.com> wrote in message >> news:7A826D5B-9241-4AD8-B165-ED61F80500B2(a)microsoft.com... >> > Does anyone know how I can insert a new column in a Gantt chart in MS >> > Project >> > 2003 that will enable me to show 'Red, Amber' Green' status of the >> > tasks? >> >> >>
|
Pages: 1 Prev: Calculate difference between dates Next: resource underallocation |