From: Gary48 on
I have a project that spans from May 06 to Jan 08. The project calander was
initially set up with holidays as non work days and a 5 day work week. I
want to change holiday non-work days to work days and change to a 7 day work
week and reflect this in completed as well as in-progress and scheduled
activities.
From: John on
In article <E8B08599-BEBB-43C9-A394-B2448A8828AD(a)microsoft.com>,
Gary48 <Gary48(a)discussions.microsoft.com> wrote:

> I have a project that spans from May 06 to Jan 08. The project calander was
> initially set up with holidays as non work days and a 5 day work week. I
> want to change holiday non-work days to work days and change to a 7 day work
> week and reflect this in completed as well as in-progress and scheduled
> activities.

Gary48,
You can change the working calendar to have a seven day work week but I
question the validity of converting company holidays to work days and
the idea of trying to do this for completed tasks makes no sense at all
- history is history - it's done.

I suggest you open the working time calendar (Tools/Change Working Time)
and starting from today, make all weekends and future holidays (if you
really must) nondefault working time. Then go to Tools/Options/Calendar
tab and set the Hours per week to be 56, assuming you are still using a
standard 8 hour work day. I wouldn't change the Days per month because
it can never truly reflect a seven day work week.

John
Project MVP
From: Gary48 on
Thanks John...and you're right about completed tasks. This helps.

Gary

"John" wrote:

> In article <E8B08599-BEBB-43C9-A394-B2448A8828AD(a)microsoft.com>,
> Gary48 <Gary48(a)discussions.microsoft.com> wrote:
>
> > I have a project that spans from May 06 to Jan 08. The project calander was
> > initially set up with holidays as non work days and a 5 day work week. I
> > want to change holiday non-work days to work days and change to a 7 day work
> > week and reflect this in completed as well as in-progress and scheduled
> > activities.
>
> Gary48,
> You can change the working calendar to have a seven day work week but I
> question the validity of converting company holidays to work days and
> the idea of trying to do this for completed tasks makes no sense at all
> - history is history - it's done.
>
> I suggest you open the working time calendar (Tools/Change Working Time)
> and starting from today, make all weekends and future holidays (if you
> really must) nondefault working time. Then go to Tools/Options/Calendar
> tab and set the Hours per week to be 56, assuming you are still using a
> standard 8 hour work day. I wouldn't change the Days per month because
> it can never truly reflect a seven day work week.
>
> John
> Project MVP
>
From: John on
In article <237B7124-945F-4AF7-9A6A-0C533D583044(a)microsoft.com>,
Gary48 <Gary48(a)discussions.microsoft.com> wrote:

> Thanks John...and you're right about completed tasks. This helps.
>
> Gary

Gary,
You're welcome and thanks for the feedback.
John
>
> "John" wrote:
>
> > In article <E8B08599-BEBB-43C9-A394-B2448A8828AD(a)microsoft.com>,
> > Gary48 <Gary48(a)discussions.microsoft.com> wrote:
> >
> > > I have a project that spans from May 06 to Jan 08. The project calander
> > > was
> > > initially set up with holidays as non work days and a 5 day work week. I
> > > want to change holiday non-work days to work days and change to a 7 day
> > > work
> > > week and reflect this in completed as well as in-progress and scheduled
> > > activities.
> >
> > Gary48,
> > You can change the working calendar to have a seven day work week but I
> > question the validity of converting company holidays to work days and
> > the idea of trying to do this for completed tasks makes no sense at all
> > - history is history - it's done.
> >
> > I suggest you open the working time calendar (Tools/Change Working Time)
> > and starting from today, make all weekends and future holidays (if you
> > really must) nondefault working time. Then go to Tools/Options/Calendar
> > tab and set the Hours per week to be 56, assuming you are still using a
> > standard 8 hour work day. I wouldn't change the Days per month because
> > it can never truly reflect a seven day work week.
> >
> > John
> > Project MVP
> >
From: "Steve House" sjhouse at hotmail dot on
Do you mean your resources will never get a day off between May and
January????? That's what setting a 7 day work-week implies - not just that
we have various work schedules that overlap to cover all 7 days of the week
but rather no one on the project team ever gets a day off between when the
project starts and when it ends. If all your resources are machines -
maybe - but human beings can't work that way.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"Gary48" <Gary48(a)discussions.microsoft.com> wrote in message
news:E8B08599-BEBB-43C9-A394-B2448A8828AD(a)microsoft.com...
>I have a project that spans from May 06 to Jan 08. The project calander
>was
> initially set up with holidays as non work days and a 5 day work week. I
> want to change holiday non-work days to work days and change to a 7 day
> work
> week and reflect this in completed as well as in-progress and scheduled
> activities.