|
From: Gary48 on 1 May 2008 20:35 I have a project that spans from May 06 to Jan 08. The project calander was initially set up with holidays as non work days and a 5 day work week. I want to change holiday non-work days to work days and change to a 7 day work week and reflect this in completed as well as in-progress and scheduled activities.
From: John on 1 May 2008 22:37 In article <E8B08599-BEBB-43C9-A394-B2448A8828AD(a)microsoft.com>, Gary48 <Gary48(a)discussions.microsoft.com> wrote: > I have a project that spans from May 06 to Jan 08. The project calander was > initially set up with holidays as non work days and a 5 day work week. I > want to change holiday non-work days to work days and change to a 7 day work > week and reflect this in completed as well as in-progress and scheduled > activities. Gary48, You can change the working calendar to have a seven day work week but I question the validity of converting company holidays to work days and the idea of trying to do this for completed tasks makes no sense at all - history is history - it's done. I suggest you open the working time calendar (Tools/Change Working Time) and starting from today, make all weekends and future holidays (if you really must) nondefault working time. Then go to Tools/Options/Calendar tab and set the Hours per week to be 56, assuming you are still using a standard 8 hour work day. I wouldn't change the Days per month because it can never truly reflect a seven day work week. John Project MVP
From: Gary48 on 2 May 2008 00:58 Thanks John...and you're right about completed tasks. This helps. Gary "John" wrote: > In article <E8B08599-BEBB-43C9-A394-B2448A8828AD(a)microsoft.com>, > Gary48 <Gary48(a)discussions.microsoft.com> wrote: > > > I have a project that spans from May 06 to Jan 08. The project calander was > > initially set up with holidays as non work days and a 5 day work week. I > > want to change holiday non-work days to work days and change to a 7 day work > > week and reflect this in completed as well as in-progress and scheduled > > activities. > > Gary48, > You can change the working calendar to have a seven day work week but I > question the validity of converting company holidays to work days and > the idea of trying to do this for completed tasks makes no sense at all > - history is history - it's done. > > I suggest you open the working time calendar (Tools/Change Working Time) > and starting from today, make all weekends and future holidays (if you > really must) nondefault working time. Then go to Tools/Options/Calendar > tab and set the Hours per week to be 56, assuming you are still using a > standard 8 hour work day. I wouldn't change the Days per month because > it can never truly reflect a seven day work week. > > John > Project MVP >
From: John on 2 May 2008 10:45 In article <237B7124-945F-4AF7-9A6A-0C533D583044(a)microsoft.com>, Gary48 <Gary48(a)discussions.microsoft.com> wrote: > Thanks John...and you're right about completed tasks. This helps. > > Gary Gary, You're welcome and thanks for the feedback. John > > "John" wrote: > > > In article <E8B08599-BEBB-43C9-A394-B2448A8828AD(a)microsoft.com>, > > Gary48 <Gary48(a)discussions.microsoft.com> wrote: > > > > > I have a project that spans from May 06 to Jan 08. The project calander > > > was > > > initially set up with holidays as non work days and a 5 day work week. I > > > want to change holiday non-work days to work days and change to a 7 day > > > work > > > week and reflect this in completed as well as in-progress and scheduled > > > activities. > > > > Gary48, > > You can change the working calendar to have a seven day work week but I > > question the validity of converting company holidays to work days and > > the idea of trying to do this for completed tasks makes no sense at all > > - history is history - it's done. > > > > I suggest you open the working time calendar (Tools/Change Working Time) > > and starting from today, make all weekends and future holidays (if you > > really must) nondefault working time. Then go to Tools/Options/Calendar > > tab and set the Hours per week to be 56, assuming you are still using a > > standard 8 hour work day. I wouldn't change the Days per month because > > it can never truly reflect a seven day work week. > > > > John > > Project MVP > >
From: "Steve House" sjhouse at hotmail dot on 4 May 2008 17:13 Do you mean your resources will never get a day off between May and January????? That's what setting a 7 day work-week implies - not just that we have various work schedules that overlap to cover all 7 days of the week but rather no one on the project team ever gets a day off between when the project starts and when it ends. If all your resources are machines - maybe - but human beings can't work that way. -- Steve House [Project MVP] MS Project Trainer & Consultant Visit http://project.mvps.org/faqs.htm for the FAQs "Gary48" <Gary48(a)discussions.microsoft.com> wrote in message news:E8B08599-BEBB-43C9-A394-B2448A8828AD(a)microsoft.com... >I have a project that spans from May 06 to Jan 08. The project calander >was > initially set up with holidays as non work days and a 5 day work week. I > want to change holiday non-work days to work days and change to a 7 day > work > week and reflect this in completed as well as in-progress and scheduled > activities.
|
Pages: 1 Prev: Resource Usage view Next: Importing Progress Data from excel |