From: M. Gawthrop on
This method requires Adobe writer.
1. Format the Gantt chart the way you want it to look.
1a. If you do not want the right hand timeline, move that off the screen
view. Do this by clicking and dragging the vertical line that separates the
timeline from your left hand columns.
1b. If you want page breaks in certain places, now is the time to set them.
1c. If you typically print in 11 x 17 format, change the page size to 8.5 x
11.
2. Print the MS Project file to Abode PDF.
2a. Check your *.pdf to make sure the columns you want are all on one page.
If not, go back to your MS Project file and adjust the column width as
necessary.

"The Cliff" wrote:

> I need to creat a shapshot of a MSProject schedule for colleague who do not
> have MSProject. Thanks in advance to anyone that can assist!