|
Prev: Micosoft Project
Next: Calculations
From: Wayne on 15 May 2008 11:41 Julie, OK I ran a baseline and my current dates (so far) are the same as my basline dates however the date when I print out the report to show slipping tasks is way past the completion date of some tasks. I thought the report would go look at the date I print and teh date on the ask and show all those tasks as slipping. So, I would like all these tasks that are not completed by the date I print the report or somehow specify, to show as slipping tasks. What am I doing wrong? Thanks soo much I have read alot of your replies and you are very helpful! Wayne "JulieS" wrote: > > "Susan" <Susan(a)discussions.microsoft.com> wrote in message > news:4DF2A616-7CBA-4788-8DE1-595E884A6F31(a)microsoft.com... > > Need assistance on how to generate a report that shows what tasks have > > not > > yet been completed by the end date specified. > > Hello Susan, > > Have you looked at the "Slipping Tasks" report in the Current Activity > category? It is a task report which shows task that have a finish date > later than the baseline finish date. > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional information > about Microsoft Project > > > >
From: JulieS on 16 May 2008 12:28 Hi Wayne, In order to see if tasks are slipping you need to make sure you update your project and then move any incomplete work forward in time. Add progress details (Actual Start, Actual Finish, Actual Work, Remaining Work etc) and then use the Update Project command in Tools > Tracking Update Project, with the option "Reschedule uncompleted tasks to start after". That will move the remaining work and duration forward to the date you specify and the slipping task report should now make much more sense. Thanks for the kind comments as well. I appreciate it :-) I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "Wayne" <Wayne(a)discussions.microsoft.com> wrote in message news:EE161A8F-3C1B-49D2-AF60-F58D6FD884B4(a)microsoft.com... > Julie, > OK I ran a baseline and my current dates (so far) are the same as my > basline > dates however the date when I print out the report to show slipping > tasks is > way past the completion date of some tasks. I thought the report > would go > look at the date I print and teh date on the ask and show all those > tasks as > slipping. > > So, I would like all these tasks that are not completed by the date > I print > the report or somehow specify, to show as slipping tasks. What am I > doing > wrong? > > Thanks soo much I have read alot of your replies and you are very > helpful! > Wayne > > "JulieS" wrote: > >> >> "Susan" <Susan(a)discussions.microsoft.com> wrote in message >> news:4DF2A616-7CBA-4788-8DE1-595E884A6F31(a)microsoft.com... >> > Need assistance on how to generate a report that shows what tasks >> > have >> > not >> > yet been completed by the end date specified. >> >> Hello Susan, >> >> Have you looked at the "Slipping Tasks" report in the Current >> Activity >> category? It is a task report which shows task that have a finish >> date >> later than the baseline finish date. >> >> I hope this helps. Let us know how you get along. >> >> Julie >> Project MVP >> >> Visit http://project.mvps.org/ for the FAQs and additional >> information >> about Microsoft Project >> >> >> >>
From: Wayne on 16 May 2008 14:44 "JulieS" wrote: > Hi Wayne, > > In order to see if tasks are slipping you need to make sure you update > your project and then move any incomplete work forward in time. Add > progress details (Actual Start, Actual Finish, Actual Work, Remaining > Work etc) and then use the Update Project command in Tools > Tracking > Update Project, with the option "Reschedule uncompleted tasks to start > after". > > That will move the remaining work and duration forward to the date you > specify and the slipping task report should now make much more sense. > > Thanks for the kind comments as well. I appreciate it :-) > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional information > about Microsoft Project > > "Wayne" <Wayne(a)discussions.microsoft.com> wrote in message > news:EE161A8F-3C1B-49D2-AF60-F58D6FD884B4(a)microsoft.com... > > Julie, > > OK I ran a baseline and my current dates (so far) are the same as my > > basline > > dates however the date when I print out the report to show slipping > > tasks is > > way past the completion date of some tasks. I thought the report > > would go > > look at the date I print and teh date on the ask and show all those > > tasks as > > slipping. > > > > So, I would like all these tasks that are not completed by the date > > I print > > the report or somehow specify, to show as slipping tasks. What am I > > doing > > wrong? > > > > Thanks soo much I have read alot of your replies and you are very > > helpful! > > Wayne > > > > "JulieS" wrote: > > > >> > >> "Susan" <Susan(a)discussions.microsoft.com> wrote in message > >> news:4DF2A616-7CBA-4788-8DE1-595E884A6F31(a)microsoft.com... > >> > Need assistance on how to generate a report that shows what tasks > >> > have > >> > not > >> > yet been completed by the end date specified. > >> > >> Hello Susan, > >> > >> Have you looked at the "Slipping Tasks" report in the Current > >> Activity > >> category? It is a task report which shows task that have a finish > >> date > >> later than the baseline finish date. > >> > >> I hope this helps. Let us know how you get along. > >> > >> Julie > >> Project MVP > >> > >> Visit http://project.mvps.org/ for the FAQs and additional > >> information > >> about Microsoft Project > >> > >> > >> > >> > Julie, Yeah it works, thanks for teaching me something new again . Have a great weekend, Wayne
From: JulieS on 16 May 2008 17:19 "Wayne" <Wayne(a)discussions.microsoft.com> wrote in message news:6C8DC46F-E9C7-46A8-A11C-F8E572BECE78(a)microsoft.com... <snip> > > Julie, > > Yeah it works, thanks for teaching me something new again . > > Have a great weekend, > Wayne You're most welcome Wayne and thanks for the feedback. Enjoy your weekend as well. Julie
|
Pages: 1 Prev: Micosoft Project Next: Calculations |