From: A. W. Dunstan on 25 Jun 2008 09:53 Fernando Rodriguez wrote: > > Hi, > > Sorry for being slightly offtopic, but I'm a bit desperate. :-) > > All my guestimates of project duration have been so far ridiculously > optimistic and I usually err by a factor of 4x or worse. > > Is there any way out of this? How can I improve my estimates? Is there ANY > book or technique worth learning? > > Any help would be greatly appreciated. Try some 'iterative refinement' as well. As the project progresses (and after it's over) compare your prediction to reality & try to understand why they don't agree. Apply what you learned the next time around. -- Al Dunstan, Software Engineer OptiMetrics, Inc. 3115 Professional Drive Ann Arbor, MI 48104-5131 |