From: mikel on 13 May 2008 18:33 Hi all what field on the import map is used to specidy a reoccuring task frequency ? i am importing from excel Thanks
From: Jack Dahlgren on 13 May 2008 20:19 There is no field on the import map which specifies task frequency. The recurring task function in Project sets up recurring tasks according to the parameters you set. I believe that the recurring task wizard is the only way that you can change the number of occurances and the frequency. -Jack Dahlgren "mikel" <mikel(a)discussions.microsoft.com> wrote in message news:5ECF9D60-C07A-4527-AA09-25F36888650D(a)microsoft.com... > Hi all > > what field on the import map is used to specidy a reoccuring task > frequency > ? i am importing from excel > > Thanks
|
Pages: 1 Prev: printing Next: Breaking the duration - start date /end date relationship |