From: genglehardt on 27 Oct 2005 16:39 How can I set up a "Level of Effort" task that starts at the beginning of a project and ends at the end of the project and will automatically extend and contract to stay equal to the project lenght if the project lenght changes due to additional tasks, overruns, etc? The LOE task is a bucket for things like answering phone calls, misc meetings, filling out time tickets, etc.
From: Brian K - Project MVP on 27 Oct 2005 17:01 genglehardt wrote: >How can I set up a "Level of Effort" task that starts at the beginning of a >project and ends at the end of the project and will automatically extend >and >contract to stay equal to the project lenght if the project lenght changes >due to additional tasks, overruns, etc? The LOE task is a bucket for >things >like answering phone calls, misc meetings, filling out time tickets, etc. http://project.mvps.org/faqs.htm Scroll down to item 19. Hammock Tasks -- Brian K - Project MVP http://www.projectified.com -- Senior Trainer - Electronic Arts -- QuantumPM Associate http://www.quantumpm.com
|
Pages: 1 Prev: BCWP <> BCWS w/ Project Status @ 100% Next: Problem starting up Project 2000 - runtime error |