From: genglehardt on
How can I set up a "Level of Effort" task that starts at the beginning of a
project and ends at the end of the project and will automatically extend and
contract to stay equal to the project lenght if the project lenght changes
due to additional tasks, overruns, etc? The LOE task is a bucket for things
like answering phone calls, misc meetings, filling out time tickets, etc.
From: Brian K - Project MVP on
genglehardt wrote:

>How can I set up a "Level of Effort" task that starts at the beginning of a
>project and ends at the end of the project and will automatically extend
>and
>contract to stay equal to the project lenght if the project lenght changes
>due to additional tasks, overruns, etc? The LOE task is a bucket for
>things
>like answering phone calls, misc meetings, filling out time tickets, etc.

http://project.mvps.org/faqs.htm

Scroll down to item 19. Hammock Tasks

--
Brian K - Project MVP
http://www.projectified.com
--
Senior Trainer - Electronic Arts
--
QuantumPM Associate
http://www.quantumpm.com