|
From: da_raw1 on 13 May 2008 13:05 Hello Everyone, When I opened my project today, I noticed that I was able to manually go into the percent complete column, at the summary level, and change that number. I thought it might be a new feature since I am using Project '03, but I went to another computer and found out it was doing it in Project '00 as well. If there is a manual override of some sorts, would someone please point me in the right direction as to where it is? -- da_raw1
From: davegb on 13 May 2008 14:55 On May 13, 11:05 am, da_raw1 <da_r...(a)hotmail.com> wrote: > Hello Everyone, > > When I opened my project today, I noticed that I was able to manually go > into the percent complete column, at the summary level, and change that > number. I thought it might be a new feature since I am using Project '03, > but I went to another computer and found out it was doing it in Project '00 > as well. If there is a manual override of some sorts, would someone please > point me in the right direction as to where it is? > -- > da_raw1 You're looking for a manual overide of being able to manually change the %Complete?
From: da_raw1 on 13 May 2008 15:04 Actually, I am able to go in and change the Summary % Completes now. I have never seen this before I wanted to know if there is an override to put it back as it should to where the subtasks calculate the Summary Line % Complete. -- da_raw1 "davegb" wrote: > On May 13, 11:05 am, da_raw1 <da_r...(a)hotmail.com> wrote: > > Hello Everyone, > > > > When I opened my project today, I noticed that I was able to manually go > > into the percent complete column, at the summary level, and change that > > number. I thought it might be a new feature since I am using Project '03, > > but I went to another computer and found out it was doing it in Project '00 > > as well. If there is a manual override of some sorts, would someone please > > point me in the right direction as to where it is? > > -- > > da_raw1 > > You're looking for a manual overide of being able to manually change > the %Complete? >
From: davegb on 13 May 2008 16:29 On May 13, 1:04 pm, da_raw1 <da_r...(a)hotmail.com> wrote: > Actually, I am able to go in and change the Summary % Completes now. I have > never seen this before I wanted to know if there is an override to put it > back as it should to where the subtasks calculate the Summary Line % Complete. Do you have resources assigned to the Summary Line? > -- > da_raw1 > > > > "davegb" wrote: > > On May 13, 11:05 am, da_raw1 <da_r...(a)hotmail.com> wrote: > > > Hello Everyone, > > > > When I opened my project today, I noticed that I was able to manually go > > > into the percent complete column, at the summary level, and change that > > > number. I thought it might be a new feature since I am using Project '03, > > > but I went to another computer and found out it was doing it in Project '00 > > > as well. If there is a manual override of some sorts, would someone please > > > point me in the right direction as to where it is? > > > -- > > > da_raw1 > > > You're looking for a manual overide of being able to manually change > > the %Complete?- Hide quoted text - > > - Show quoted text -
From: JulieS on 13 May 2008 17:14 On May 13, 1:04 pm, da_raw1 <da_r...(a)hotmail.com> wrote: > Actually, I am able to go in and change the Summary % Completes now. > I have > never seen this before I wanted to know if there is an override to > put it > back as it should to where the subtasks calculate the Summary Line % > Complete. "davegb" wrote in message Do you have resources assigned to the Summary Line? <snip> Pardon me for bumping in, but I don't think this is new behavior. I believe if you enter % complete on a summary task line, it will distribute the % complete to the subtasks based upon expected % complete. For example: if you have a summary with an 8 day duration with 4 subtasks all linked F to S with 2 days duration each. Enter 50% complete on the summary task and project will mark the first two days as 100% complete with the last two tasks remaining 0%. The summary task is 50% complete of 8 days (4 days actual and 4 days remaining). If you change the second subtask to 50% complete, the summary task % complete updates to 38% -- 3 actual days duration out of a total of 8. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project
|
Next
|
Last
Pages: 1 2 Prev: When I open a MSP file, my task numbers are out of sequence. Next: Project 2003 - alignment |