From: Baggy on
I have a plan with over 400 tasks which is split into a number sections.
When I view the plan as a Network Diagram it show all the task/subtasks from
start to finish of the Project. Is it possible to just to select what can be
displayed as a Network Diagram.
If so, I'd like to be able to (i) select particular tasks/subtasks e.g. line
40 to 70 to be shown only (ii) select a timescale e.g. 1 February to 1 April
to be shown only.

Any advice would be greatly appreciated.
From: Mike Glen on
Hi Baggy,

Welcome to this Microsoft Project newsgroup :)

You can use Project/Filtered for.../More filters and choose from what is
offered.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

Baggy wrote:
> I have a plan with over 400 tasks which is split into a number
> sections.
> When I view the plan as a Network Diagram it show all the
> task/subtasks from start to finish of the Project. Is it possible to
> just to select what can be displayed as a Network Diagram.
> If so, I'd like to be able to (i) select particular tasks/subtasks
> e.g. line 40 to 70 to be shown only (ii) select a timescale e.g. 1
> February to 1 April to be shown only.
>
> Any advice would be greatly appreciated.



From: "Michael Manukau Inst of Technology NZ" <Michael Manukau Inst of Technology on
Hi Mike,
I created a copy of the 'Summary tasks' filter, changed it to 'Summary =
No', but the Summary task didn't disappear. I didn't try it in the Gantt,
only in the Network Diagram view.
I find the display of summary tasks in the Network Diagram view very poor.
Best would be a line around the subtasks, but to show a summary as just
another task is less than helpful, to my way of thinking.
Look forward to trying any more ideas.


"Mike Glen" wrote:

> Hi Baggy,
>
> Welcome to this Microsoft Project newsgroup :)
>
> You can use Project/Filtered for.../More filters and choose from what is
> offered.
>
> FAQs, companion products and other useful Project information can be seen at
> this web address: http://project.mvps.org/faqs.htm
>
> Hope this helps - please let us know how you get on :)
>
> Mike Glen
> MS Project MVP
>
> Baggy wrote:
> > I have a plan with over 400 tasks which is split into a number
> > sections.
> > When I view the plan as a Network Diagram it show all the
> > task/subtasks from start to finish of the Project. Is it possible to
> > just to select what can be displayed as a Network Diagram.
> > If so, I'd like to be able to (i) select particular tasks/subtasks
> > e.g. line 40 to 70 to be shown only (ii) select a timescale e.g. 1
> > February to 1 April to be shown only.
> >
> > Any advice would be greatly appreciated.
>
>
>
>
From: "JulieS" <passport6847 at maine dot rr dot on
Hi Michael,

You can turn off the display of summary tasks in the Network diagram by
choosing, Format > Layout. Under Box Layout, uncheck Show summary tasks.
You could then use the Date Range... filter to filter only for a specific
date range of tasks.

I hope this helps. Let us know how you get along.

Julie
"Michael Manukau Inst of Technology NZ" <Michael Manukau Inst of Technology
NZ(a)discussions.microsoft.com> wrote in message
news:6C1DDF3E-CD52-4F19-9454-4EEC51F7CB0A(a)microsoft.com...
> Hi Mike,
> I created a copy of the 'Summary tasks' filter, changed it to 'Summary =
> No', but the Summary task didn't disappear. I didn't try it in the Gantt,
> only in the Network Diagram view.
> I find the display of summary tasks in the Network Diagram view very poor.
> Best would be a line around the subtasks, but to show a summary as just
> another task is less than helpful, to my way of thinking.
> Look forward to trying any more ideas.
>
>
> "Mike Glen" wrote:
>
>> Hi Baggy,
>>
>> Welcome to this Microsoft Project newsgroup :)
>>
>> You can use Project/Filtered for.../More filters and choose from what is
>> offered.
>>
>> FAQs, companion products and other useful Project information can be seen
>> at
>> this web address: http://project.mvps.org/faqs.htm
>>
>> Hope this helps - please let us know how you get on :)
>>
>> Mike Glen
>> MS Project MVP
>>
>> Baggy wrote:
>> > I have a plan with over 400 tasks which is split into a number
>> > sections.
>> > When I view the plan as a Network Diagram it show all the
>> > task/subtasks from start to finish of the Project. Is it possible to
>> > just to select what can be displayed as a Network Diagram.
>> > If so, I'd like to be able to (i) select particular tasks/subtasks
>> > e.g. line 40 to 70 to be shown only (ii) select a timescale e.g. 1
>> > February to 1 April to be shown only.
>> >
>> > Any advice would be greatly appreciated.
>>
>>
>>
>>


From: Mike Glen on
Try Tools/Options/View tab and at the bottom, deselect the summary and
project summary check marks.

Mike Glen
Project MVP

Michael Manukau Inst of Technology NZ wrote:
> Hi Mike,
> I created a copy of the 'Summary tasks' filter, changed it to
> 'Summary = No', but the Summary task didn't disappear. I didn't try
> it in the Gantt, only in the Network Diagram view.
> I find the display of summary tasks in the Network Diagram view very
> poor. Best would be a line around the subtasks, but to show a summary
> as just another task is less than helpful, to my way of thinking.
> Look forward to trying any more ideas.
>
>
> "Mike Glen" wrote:
>
>> Hi Baggy,
>>
>> Welcome to this Microsoft Project newsgroup :)
>>
>> You can use Project/Filtered for.../More filters and choose from
>> what is offered.
>>
>> FAQs, companion products and other useful Project information can be
>> seen at this web address: http://project.mvps.org/faqs.htm
>>
>> Hope this helps - please let us know how you get on :)
>>
>> Mike Glen
>> MS Project MVP
>>
>> Baggy wrote:
>>> I have a plan with over 400 tasks which is split into a number
>>> sections.
>>> When I view the plan as a Network Diagram it show all the
>>> task/subtasks from start to finish of the Project. Is it possible
>>> to just to select what can be displayed as a Network Diagram.
>>> If so, I'd like to be able to (i) select particular tasks/subtasks
>>> e.g. line 40 to 70 to be shown only (ii) select a timescale e.g. 1
>>> February to 1 April to be shown only.
>>>
>>> Any advice would be greatly appreciated.



 | 
Pages: 1
Prev: Macro manage projects
Next: Adust Dates macro.