|
Prev: How can I change the height of a task as it is shown in MSP?
Next: Need syntax to link ghost tasks
From: Kevlin on 5 May 2008 16:21 Hello, I am new to the forums and only recently started using MS Project 2003. I am wondering how I would go about the following: First a bit of history, we track our projects from a single date this date really is not a start or a finish but more of a work date. When we do this we go forwards and backwards in time by using + and - d Example say our project is supposed to start on 1 Jan 08, before that can start we must start a test plan and many other steps. So our Finish date (for lack of better things to call it) is 1 Jan 08 our Test plan is built - 120 days so that would be 1 Sep 07. Likewise we do a report that is due + 90 days so that would be 1 Apr 08. How would I use this as a formula to calculate the dates these need to start for me. I envision a task sheet with fields labled Task Name Duration Lag/Lead Start Date Finish Date Where Duration would be typed in and lead to a finish date based on the Lag/Lead column inputting to the Start date Example Task Name Test Plan 20d -120d (calculated Finish date -120d = 1 Sep 07) 21 Sep 07 Any ideas on how to build the formula and put it into a column? I apologize, if this has been asked a zillion times and also for my newbie'sm Cheers, -- Kevlin ------------------------------------------------------------------------ Kevlin's Profile: http://forums.techarena.in/member.php?userid=48295 View this thread: http://forums.techarena.in/showthread.php?t=962433 http://forums.techarena.in
From: DavidC on 5 May 2008 17:55 Hi, If the 1st Jan is the earliest date the project can start, then set that as the start date and make it a milestone (zero duration). Then all activities will be successors to this. Since you need to create a test plan which will take 20d to create and let us say it needs to be reviewed and agreed before the project starts, then you can set up the project so that: Project start 0d 1/01/09 Test plan agreed 5d Test plan review and amend 15d Develop test plan 20d. Now the successor to the Project start is then the Test plan agreed with a SF type link, the Test plan review is also a SF successor to the Test plan agreed, and the Test plan development is a SF successor to the test plan review. This then gives you the latest date by which you need to start the test plan in order to meet the project start date. I would then recommend allowing for some float in this process since it is unlikely for things to work exactly to plan. So maybe increase the durations by 10% thereby giving you say 10% float before project start date. Also place a deadline on the Test plan agreed date as being the start date for the project less one day. This will then identify the critical path for that process leading up to the project start. Alternatively place the deadline as above, but make the links to the Project start date as FS predecessors not as above. This will mean putting a start date for developing the plan. Just a couple of ideas Hope this helps. Regardd DavidC "Kevlin" wrote: > > Hello, I am new to the forums and only recently started using MS Project > 2003. > > I am wondering how I would go about the following: > > First a bit of history, we track our projects from a single date this > date really is not a start or a finish but more of a work date. > > When we do this we go forwards and backwards in time by using + and - > d > > Example say our project is supposed to start on 1 Jan 08, before that > can start we must start a test plan and many other steps. > > So our Finish date (for lack of better things to call it) is 1 Jan 08 > our Test plan is built - 120 days so that would be 1 Sep 07. Likewise > we do a report that is due + 90 days so that would be 1 Apr 08. > > How would I use this as a formula to calculate the dates these need to > start for me. > > I envision a task sheet with fields labled > Task Name Duration Lag/Lead Start Date Finish Date > > Where Duration would be typed in and lead to a finish date based on the > Lag/Lead column inputting to the Start date > > Example > > Task Name > Test Plan 20d -120d (calculated Finish date > -120d = 1 Sep 07) 21 Sep 07 > > Any ideas on how to build the formula and put it into a column? > > I apologize, if this has been asked a zillion times and also for my > newbie'sm > > Cheers, > > > -- > Kevlin > ------------------------------------------------------------------------ > Kevlin's Profile: http://forums.techarena.in/member.php?userid=48295 > View this thread: http://forums.techarena.in/showthread.php?t=962433 > > http://forums.techarena.in > >
From: dlmckirdy on 5 May 2008 18:51 Kevlin, Why not first set your start date to 1/1/08. Then build your schedule Top Down (start to finish) as normal. When you are done, go to Project>Project Information>Start Date and adjust the start date until your "Work Date" hits the desired date. Do not schedule by dates, but rather by duration, letting Project determine the dates. Then, assuming there are no duration changes prior to the "Work Date", all scheduling is in direct relation to the "Work Date". -- Douglas McKirdy Project Analyst "Kevlin" wrote: > > Hello, I am new to the forums and only recently started using MS Project > 2003. > > I am wondering how I would go about the following: > > First a bit of history, we track our projects from a single date this > date really is not a start or a finish but more of a work date. > > When we do this we go forwards and backwards in time by using + and - > d > > Example say our project is supposed to start on 1 Jan 08, before that > can start we must start a test plan and many other steps. > > So our Finish date (for lack of better things to call it) is 1 Jan 08 > our Test plan is built - 120 days so that would be 1 Sep 07. Likewise > we do a report that is due + 90 days so that would be 1 Apr 08. > > How would I use this as a formula to calculate the dates these need to > start for me. > > I envision a task sheet with fields labled > Task Name Duration Lag/Lead Start Date Finish Date > > Where Duration would be typed in and lead to a finish date based on the > Lag/Lead column inputting to the Start date > > Example > > Task Name > Test Plan 20d -120d (calculated Finish date > -120d = 1 Sep 07) 21 Sep 07 > > Any ideas on how to build the formula and put it into a column? > > I apologize, if this has been asked a zillion times and also for my > newbie'sm > > Cheers, > > > -- > Kevlin > ------------------------------------------------------------------------ > Kevlin's Profile: http://forums.techarena.in/member.php?userid=48295 > View this thread: http://forums.techarena.in/showthread.php?t=962433 > > http://forums.techarena.in > >
From: "Steve House" sjhouse at hotmail dot on 6 May 2008 11:18 I've gotta agree with Douglas here. Perhaps it's time to re-examine your approach to project scheduling in general. MS Project, and indeed the foundations of critical path managment methodology, says that the Project Start is when the first activity leading towards creation of the project's deliverables commences. In your example, the real project start is the date of the start of the first activity in your Test Plan. The Start of Work is the beginning of a project phase that comes well after the start of the project itself. The problem with the method you propose is that it requires a fair amount of clairvoyance and that's a talent in short supply ever since Casandra retired. Better to calculate when you'll be able to start work rather than try to foretell the future and work backwards from the date your psychic predicts you'll start. <grin> -- Steve House [Project MVP] MS Project Trainer & Consultant Visit http://project.mvps.org/faqs.htm for the FAQs "Kevlin" <Kevlin.38yhnc(a)DoNotSpam.com> wrote in message news:Kevlin.38yhnc(a)DoNotSpam.com... > > Hello, I am new to the forums and only recently started using MS Project > 2003. > > I am wondering how I would go about the following: > > First a bit of history, we track our projects from a single date this > date really is not a start or a finish but more of a work date. > > When we do this we go forwards and backwards in time by using + and - > d > > Example say our project is supposed to start on 1 Jan 08, before that > can start we must start a test plan and many other steps. > > So our Finish date (for lack of better things to call it) is 1 Jan 08 > our Test plan is built - 120 days so that would be 1 Sep 07. Likewise > we do a report that is due + 90 days so that would be 1 Apr 08. > > How would I use this as a formula to calculate the dates these need to > start for me. > > I envision a task sheet with fields labled > Task Name Duration Lag/Lead Start Date Finish Date > > Where Duration would be typed in and lead to a finish date based on the > Lag/Lead column inputting to the Start date > > Example > > Task Name > Test Plan 20d -120d (calculated Finish date > -120d = 1 Sep 07) 21 Sep 07 > > Any ideas on how to build the formula and put it into a column? > > I apologize, if this has been asked a zillion times and also for my > newbie'sm > > Cheers, > > > -- > Kevlin > ------------------------------------------------------------------------ > Kevlin's Profile: http://forums.techarena.in/member.php?userid=48295 > View this thread: http://forums.techarena.in/showthread.php?t=962433 > > http://forums.techarena.in >
From: salgud on 6 May 2008 13:43 On Tue, 6 May 2008 11:18:01 -0400, Steve House wrote: > I've gotta agree with Douglas here. Perhaps it's time to re-examine your > approach to project scheduling in general. MS Project, and indeed the > foundations of critical path managment methodology, says that the Project > Start is when the first activity leading towards creation of the project's > deliverables commences. In your example, the real project start is the date > of the start of the first activity in your Test Plan. The Start of Work is > the beginning of a project phase that comes well after the start of the > project itself. > > The problem with the method you propose is that it requires a fair amount of > clairvoyance and that's a talent in short supply ever since Casandra > retired. Better to calculate when you'll be able to start work rather than > try to foretell the future and work backwards from the date your psychic > predicts you'll start. <grin> Well put, Steve!
|
Next
|
Last
Pages: 1 2 Prev: How can I change the height of a task as it is shown in MSP? Next: Need syntax to link ghost tasks |