From: Lee on
When in calendar view, all tasks appear to be indented about 10 spaces. Is
it possible to align the tasks on the left?
--
Lee
From: JulieS on
Hi Lee,

Try Format > Bar Styles and check (enable) Bar Rounding.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Lee" <Lee(a)discussions.microsoft.com> wrote in message
news:36DF55A4-42B6-4F84-94EF-B9D20A802B0C(a)microsoft.com...
> When in calendar view, all tasks appear to be indented about 10
> spaces. Is
> it possible to align the tasks on the left?
> --
> Lee


From: Lee on
Julie:
Thanks for the prompt reply. I tried your suggestion but I still have the
indents. Any other suggestions? --
Lee


"JulieS" wrote:

> Hi Lee,
>
> Try Format > Bar Styles and check (enable) Bar Rounding.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
>
> "Lee" <Lee(a)discussions.microsoft.com> wrote in message
> news:36DF55A4-42B6-4F84-94EF-B9D20A802B0C(a)microsoft.com...
> > When in calendar view, all tasks appear to be indented about 10
> > spaces. Is
> > it possible to align the tasks on the left?
> > --
> > Lee
>
>
>
From: JulieS on
Hi Lee,

I assume you are talking about the Calendar View not the left side of
the Gantt chart?

The small amount the task is indented from the edge of the block
representing the date in Calendar view does not appear to change --
even if I change the start and finish of the task.

Julie
"Lee" <Lee(a)discussions.microsoft.com> wrote in message
news:74F54D15-8E0C-4861-B6D9-1E91391BF644(a)microsoft.com...
> Julie:
> Thanks for the prompt reply. I tried your suggestion but I still
> have the
> indents. Any other suggestions? --
> Lee
>
>
> "JulieS" wrote:
>
>> Hi Lee,
>>
>> Try Format > Bar Styles and check (enable) Bar Rounding.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information
>> about Microsoft Project
>>
>>
>> "Lee" <Lee(a)discussions.microsoft.com> wrote in message
>> news:36DF55A4-42B6-4F84-94EF-B9D20A802B0C(a)microsoft.com...
>> > When in calendar view, all tasks appear to be indented about 10
>> > spaces. Is
>> > it possible to align the tasks on the left?
>> > --
>> > Lee
>>
>>
>>


From: Lee on
Julie:
I reinstalled the program and now the bar rounding solves the problem.
Thanks.
--
Lee


"JulieS" wrote:

> Hi Lee,
>
> Try Format > Bar Styles and check (enable) Bar Rounding.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
>
> "Lee" <Lee(a)discussions.microsoft.com> wrote in message
> news:36DF55A4-42B6-4F84-94EF-B9D20A802B0C(a)microsoft.com...
> > When in calendar view, all tasks appear to be indented about 10
> > spaces. Is
> > it possible to align the tasks on the left?
> > --
> > Lee
>
>
>