From: Lee on 13 May 2008 14:58 When in calendar view, all tasks appear to be indented about 10 spaces. Is it possible to align the tasks on the left? -- Lee
From: JulieS on 13 May 2008 15:31 Hi Lee, Try Format > Bar Styles and check (enable) Bar Rounding. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "Lee" <Lee(a)discussions.microsoft.com> wrote in message news:36DF55A4-42B6-4F84-94EF-B9D20A802B0C(a)microsoft.com... > When in calendar view, all tasks appear to be indented about 10 > spaces. Is > it possible to align the tasks on the left? > -- > Lee
From: Lee on 13 May 2008 16:09 Julie: Thanks for the prompt reply. I tried your suggestion but I still have the indents. Any other suggestions? -- Lee "JulieS" wrote: > Hi Lee, > > Try Format > Bar Styles and check (enable) Bar Rounding. > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional information > about Microsoft Project > > > "Lee" <Lee(a)discussions.microsoft.com> wrote in message > news:36DF55A4-42B6-4F84-94EF-B9D20A802B0C(a)microsoft.com... > > When in calendar view, all tasks appear to be indented about 10 > > spaces. Is > > it possible to align the tasks on the left? > > -- > > Lee > > >
From: JulieS on 13 May 2008 16:19 Hi Lee, I assume you are talking about the Calendar View not the left side of the Gantt chart? The small amount the task is indented from the edge of the block representing the date in Calendar view does not appear to change -- even if I change the start and finish of the task. Julie "Lee" <Lee(a)discussions.microsoft.com> wrote in message news:74F54D15-8E0C-4861-B6D9-1E91391BF644(a)microsoft.com... > Julie: > Thanks for the prompt reply. I tried your suggestion but I still > have the > indents. Any other suggestions? -- > Lee > > > "JulieS" wrote: > >> Hi Lee, >> >> Try Format > Bar Styles and check (enable) Bar Rounding. >> >> I hope this helps. Let us know how you get along. >> >> Julie >> Project MVP >> >> Visit http://project.mvps.org/ for the FAQs and additional >> information >> about Microsoft Project >> >> >> "Lee" <Lee(a)discussions.microsoft.com> wrote in message >> news:36DF55A4-42B6-4F84-94EF-B9D20A802B0C(a)microsoft.com... >> > When in calendar view, all tasks appear to be indented about 10 >> > spaces. Is >> > it possible to align the tasks on the left? >> > -- >> > Lee >> >> >>
From: Lee on 13 May 2008 16:33 Julie: I reinstalled the program and now the bar rounding solves the problem. Thanks. -- Lee "JulieS" wrote: > Hi Lee, > > Try Format > Bar Styles and check (enable) Bar Rounding. > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional information > about Microsoft Project > > > "Lee" <Lee(a)discussions.microsoft.com> wrote in message > news:36DF55A4-42B6-4F84-94EF-B9D20A802B0C(a)microsoft.com... > > When in calendar view, all tasks appear to be indented about 10 > > spaces. Is > > it possible to align the tasks on the left? > > -- > > Lee > > >
|