From: Senbag on
I read the Available Fields KB and found that there is a new field called
Expected Finish. Can I use the field for entering expected completed date of
a task?
The artcle also says that the actual field to use is Finish2. When I use it,
can I change that to Expected finish as a caption?

Is there anyway, I can greyout the column in My task assignment view?
From: Mike Glen on
Hi Senbag,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP



"Senbag" <Senbag(a)discussions.microsoft.com> wrote in message
news:AE7013BB-65BB-4489-9D8B-20EBF456A4FC(a)microsoft.com...
>I read the Available Fields KB and found that there is a new field called
> Expected Finish. Can I use the field for entering expected completed date
> of
> a task?
> The artcle also says that the actual field to use is Finish2. When I use
> it,
> can I change that to Expected finish as a caption?
>
> Is there anyway, I can greyout the column in My task assignment view?


From: Senbag on
Mike,
I couldn't find any answers for my questions. Since I am pretty new to this
user forum, please send me the link where I can post my questions. I posted
my questions since i have found similar questions in this forumn.

any help on my questions is appreciated
Thanks in advance.

Senbag

"Mike Glen" wrote:

> Hi Senbag,
>
> Try posting on the server newsgroup. Please see FAQ Item: 24. Project
> Newsgroups. FAQs, companion products and other useful Project information
> can be seen at this web address: http://project.mvps.org/faqs.htm
>
> Mike Glen
> Project MVP
>
>
>
> "Senbag" <Senbag(a)discussions.microsoft.com> wrote in message
> news:AE7013BB-65BB-4489-9D8B-20EBF456A4FC(a)microsoft.com...
> >I read the Available Fields KB and found that there is a new field called
> > Expected Finish. Can I use the field for entering expected completed date
> > of
> > a task?
> > The artcle also says that the actual field to use is Finish2. When I use
> > it,
> > can I change that to Expected finish as a caption?
> >
> > Is there anyway, I can greyout the column in My task assignment view?
>
>
>
From: JulieS on
Hello Senbag,

Try the following link for the project server newsgroup:

http://www.microsoft.com/office/community/en-us/default.mspx?dg=microsoft.public.project.server&lang=en&cr=US

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Senbag" <Senbag(a)discussions.microsoft.com> wrote in message
news:BFBC728B-D038-4C3D-8270-1B3F9D7EE432(a)microsoft.com...
> Mike,
> I couldn't find any answers for my questions. Since I am pretty new
> to this
> user forum, please send me the link where I can post my questions. I
> posted
> my questions since i have found similar questions in this forumn.
>
> any help on my questions is appreciated
> Thanks in advance.
>
> Senbag
>
> "Mike Glen" wrote:
>
>> Hi Senbag,
>>
>> Try posting on the server newsgroup. Please see FAQ Item: 24.
>> Project
>> Newsgroups. FAQs, companion products and other useful Project
>> information
>> can be seen at this web address: http://project.mvps.org/faqs.htm
>>
>> Mike Glen
>> Project MVP
>>
>>
>>
>> "Senbag" <Senbag(a)discussions.microsoft.com> wrote in message
>> news:AE7013BB-65BB-4489-9D8B-20EBF456A4FC(a)microsoft.com...
>> >I read the Available Fields KB and found that there is a new field
>> >called
>> > Expected Finish. Can I use the field for entering expected
>> > completed date
>> > of
>> > a task?
>> > The artcle also says that the actual field to use is Finish2.
>> > When I use
>> > it,
>> > can I change that to Expected finish as a caption?
>> >
>> > Is there anyway, I can greyout the column in My task assignment
>> > view?
>>
>>
>>