Entering actual hours does not move remaining work beyond Status D
I have Fixed Units tasks (not Effort Driven) and the Options "Move end of completed parts after status date back to status date" and "Move start of remaining parts before status date forward to status date" and "Split in-progress tasks" set. When I update a task status by increasing the "% Complete" manually, ... 24 Apr 2008 18:13
Merged projects resource graph??
I have merged two projects in MSP 2003 (using window/new window) that contain the same resource names, however MSP is not giving me an 'all up' resource number based on the sum of both projects. What it does give me is the resource graph twice based on the individaul data for each project, but not a combined t... 25 Apr 2008 14:09
Install Project 2007 fails with "missing upgrade product" message
I have a full copy of Project Pro 2007. After installing Office Enterprise, then Visio and Expression Web from the same DVD, I attempt to install Project Pro. This fails with a message saying that it cannot find a qualifying installation to upgrade from. The machine is Vista Ultimate fresh install and there ... 22 Apr 2008 08:54
Is Project the answer?
We are trying to use Project for job-shop scheduling. Can anyone tell me is this program is correct for this? ... 22 Apr 2008 11:34
Hyperlink base
Hi, I'm export/importing MS Project templates in XML format, and I'm using relative paths as URL:s. How can I save also hyperlink base address in XML format? thanks, Henrik ... 22 May 2008 02:57
Progressing a project
Hi all, I have marked some tasks as 100% complete, but when I try Tools, Tracking, Update Project - I get "did not reschedule some tasks" because of constraints. I'm a bit confused by this "Update Project". Is it really necessary to run this. Can't I just do a level on the project? Many thanks, Mark ... 25 Apr 2008 21:58
How can I print calendar type against activities in MSproject?
I want to get calendar type printed againste activities in Microsoft project print out. Can somebody help me how to get this printed ... 22 Apr 2008 01:32
Compare Project Versions Utility
I have a program with a master file and some subproject files. We link between the subproject files. Data is submitted from a subcontractor monthly. So, we have folders for each month end of data. That is, the Master.mpp and its subprojects are all stored in a monthly folder... J08, F08, etc. We can detect ... 23 Apr 2008 11:41
MS Project 2007 Entering hours on its own
I am updating a project plan in which the baseline hours were 16. I enter 4 for hours worked and then 5 for remaining. The next thing I know, MS Project enters 2000 hours. I go back change the hours and then it adds 3000 to another project. I tried to call Microsost but unless I pay them - I cant talk with... 22 Apr 2008 01:32
MSP2000- Removing resource allocation from pool if MPP file is
Thank you Dale, that worked great. "Dale Howard [MVP]" wrote: David D -- Open the resource pool file Read/Write and then click Tools - Resource Sharing - Share Resources. In the Share Resources dialog, you will find a list of projects that are sharing files with the resources in the resource ... 21 Apr 2008 20:32