job sheets being too vague
I work at a manufacturing company and I am trying to put together project timelines based on jobsheets handed in each week and it is my first time working with microsoft project. The problem I am having is that sometimes the job sheets are too vague (for example "welding - 10 hrs") and I can't put the hours tow... 23 Apr 2008 14:06
If I know PC version of Project2003, how does that compare to an Apple version?
I'm not sure what Apple version my friend has. But it is Project, running on his Apple computer. Thanks, if anyone knows the answer. ... 23 Apr 2008 13:18
Completion links
How can I Link the completion date of a task to coincide with the completion date of another task? ... 24 Apr 2008 11:01
Calculating two costs in Project 2003
I have set up a project in Project Pro 2003 with the chargeable rates for each resource in rate table A. As well as the total costs using these rates, I have also to calculate task and total costs using a discounted rate for each resource. If you like, this is a 'retail' rate and an 'internal' rate, or the diffe... 26 Apr 2008 09:09
how do I show vertical deadlines in project
I am trying to show a deadline vertically rather than as a milestone, is this possible? I have checked out progress lines but doesnt seem to quite do what I want! ... 23 Apr 2008 11:41
Task leveling...
I am new to project 2007 and am having some issues with resource leveling. I am NOT using project server but do have a resource Pool set up that I am using for a few projects. The issue I am having is when I try and scheule a task that takes more hours then there are in a single day ie 10 hours, and I level r... 24 Apr 2008 18:13
Fractions in the summary task duration
I am confused as to why I am getting 1/3 and 2/3 fractions of days in a couple of my summary task durations.....Thanks ... 23 Apr 2008 11:41
finish date
I'm a rookie at Projects, so please be patent with me Is there a way to freeze the finish date so when I put in or change a duration (hours) it changes the start date not the finish date? -- JB ... 23 Apr 2008 12:29
Can not add toolbars
I have Projects 2002 Standard on Windows 2000 OS. It started a few weeks ago not being able to see all my tools bars. I have formatting toolbar but thats all. I went to re-select other toolbars but it will not allow me to place a check mark by any other toolbar. I can add a custom, but thats all. Please he... 23 Apr 2008 18:06
Tracking against Baseline 1 - 10
How can I get the "Tracking Gantt" as comparison not to "Baseline", but to one of the additional Baselines 1 - 10? I did only found the view "Multiple Baselines Gantt", but this option does not show the comparison to the actual schedule. Regards Claus ... 23 Apr 2008 10:53