Entering actual hours does not move remaining work beyond Stat
JulieS - Thanks! That did the trick. You are a lifesaver. - BlaiseR -- Thanks. "JulieS" wrote: Hello BlaiseR, No, you're not missing a setting. As you note, incomplete work is only shifted when you update using % complete or enter actual work in a non-time phased view (neither Task nor Re... 25 Apr 2008 11:48
BCWS and basline work do not end up the same
We perform hardware and software maintenance actions, and have to constantly add tasks ranging from weeks to years to the overall plan. As such, some of the tasks are always going to be complete and some not. The problem we are having is that after adding tasks to a plan and saving them to the baseline, the b... 30 Apr 2008 10:09
2007 Crashes When Saving Second Linked File Off Server
When saving from 2007 server to a hard drive, I want to avoid having files saved off of the server linked to files on the server. To verify this capability, I created two two-task schedules linked to each other and saved them on the server. When testing, I opened both files then tried to save each of them as of... 19 May 2008 15:24
How to adjust calendar in MSP 2003
I used MSP 2007 Professional in my personal computer and I get accustomed to it. But in my company, the version they use is MSP 2003 Standard and I got some problem with the calendar adjustment. There is no button for me to adjust the work week as I did with MSP 2007. MSP 2003 only allows some exception adju... 25 Apr 2008 06:04
View Initials on resources
I have a simple question, in the gantt view, how do you view initials against tasks rather than full names? -- MjJack ------------------------------------------------------------------------ MjJack's Profile: http://forums.techarena.in/member.php?userid=47313 View this thread: http://forums.techarena.in/showthread.... 25 Apr 2008 06:04
checking projects for errors
Hi -I am using 2003 and have a plan that has 350 lines, i think its OK but we have introduced a lot of constraints with start dates.. Is there a way of checking to see if there are additional conflict errors in the plan. I am getting some conflict statements but when i check them and press the "cancel" they... 30 Apr 2008 10:56
default task settings (priority and constraint type)
I've dug through the archives, and it appears that in the past there has been no way to change a new task's priority to something other than 500. I wanted to bring this question up again for people who are familiar with Project 2007. There are two values in my current setting that I really want to change the de... 24 Apr 2008 16:37
How set milestone so it is linked to last step in critical path
I want to create a milestone for an after action review. This can not take place until all other items are completed. If a task gets delayed, then the review milestone will need to be delayed. So my question is: can this milestone link be dynamic so it automatically comes after whatever task happens to have ... 24 Apr 2008 15:01
Summarizing tasks not adding up.
My summary tasks are not working correctly(as far as I can see). In the following the Windows Service task is showing as 156 hours and the 3 task it is summarizing = 88???? The Testing and Installation task is showing 32 when it should be 28??? Task Hours Pred 1Project ... 21 May 2008 09:42
Project Server file not matching Project Web file
We are using Project Prof 2003. We have been using it for a couple years without this issue, but lately, updates made to the .mpp through MS Project are not all showing up when viewing the project on the web. Have tried republishing and clearing out cache, but didn't help. Any suggestions? ... 25 Apr 2008 14:56