Schedule portion of days
I have tasks that will be completed over a multliple-day period. However, the resources assigned to the task will only work a part of each day on the task. How do I allocate that with Project? ... 29 Apr 2008 22:59
Calender time not the same as task time?
Hello I set up my standart calender with workday from 08:15-12:30 / 13:00-16:45. When i link a resource to this calender and to the tasks. I made a test with a week with every day one task with one day duration. Now the first day is start 28-04-2008 / 08:15 and end 28-04-2008 / 16:45. The other day gave me s... 1 May 2008 16:06
Physical % Complete Summary Rollup
Hi Jim, Excuse me piggy backing this query. I am working towards a solution for showing %complete on a group by outline view. From what you have written I need to set EV Method = Physical % Complete. I have done this by selecting all tasks and setting Physical % Complete. However it does not seem to have... 4 May 2008 11:07
Soft Links
We've just implimented Enterprise and the PM keeps talking about soft links causing problems? what are soft links in this context and why are they causing problems? ... 30 Apr 2008 02:07
Is There A New Task Flag?
Here is my problem. I have to be able to identify new tasks that have been added since a schedule was baselined. I would like to create a filter to single these out, but I don't know what field to filter against. ... 30 Apr 2008 21:55
Disappearing and Out of Order Tasks
I have this extremely strange problem which I hope someone may have seen before and knows how to fix it. I have a schedule where certain tasks seem to disappear when opening the file. For instance, I will see tasks IDs 4 and 6 but task 5 is not there. There is no filter or autofilter turned on. If I tried to do a... 30 Apr 2008 14:52
Bar, then dotted line - why??
I have an activity that is 96 hours long with various resources against it, however MSP is only giving me a bar for the first 24 hours, then a dotted line for the remainder of the task. Consequently my resource profile only shows up against the first 24 hours of this task. The resource calenders are set up ... 29 Apr 2008 22:59
Can Project import tasks from other MS Products?
My team is asking if MS Project can hold all the data a database could hold. Task detail - who they called - when - follow-up notifications. I don't know if this is possible with MS Project. I've only used Project for scheduling. Any comments or thoughts would be greatly appreciated. -- KimR ... 30 Apr 2008 14:52
Project Ver - Can Project 2003 Pro and Std. Work on a Shared Drv?
Windows XP Pro, SP2; MS Office 2003 SP3 with mixed environment of either Project 2003 Professional or Project 2003 Standard. I've just been informed of this issue and am new to Project; I have searched on various sites as well. We have a large dashboard/main project located on a shared drive with numerous li... 29 Apr 2008 16:43
Showing Non-Working Time
I was just wondering if there is any other way of showing non-working time on the Gantt Chart without having to put the bottom tier into days? Cheers Gary. -- Project for Work, Cigars for Pleasure ... 29 Apr 2008 12:00