What's the best way to export from Project to other MS programs? Ways that do not work well 1. PowerPoint has a tool in the View, Toolbars, Analysis. This toolbar has several options for manipulating a Gantt chart into other MS products, but none captured the entire project. Basically, I found this to import screen shots. However, you may want to play with it and see if it fi... 30 Apr 2008 14:05
MS project gantt into powerpoint Ways that do not work well 1. PowerPoint has a tool in the View, Toolbars, Analysis. This toolbar has several options for manipulating a Gantt chart into other MS products, but none captured the entire project. Basically, I found this to import screen shots. However, you may want to play with it and see if it fi... 30 Apr 2008 14:05
Template used by Project 2003 to produce powerpoint slide Ways that do not work well 1. PowerPoint has a tool in the View, Toolbars, Analysis. This toolbar has several options for manipulating a Gantt chart into other MS products, but none captured the entire project. Basically, I found this to import screen shots. However, you may want to play with it and see if it fi... 30 Apr 2008 14:05
How do I convert a Project page to pdf? This method requires Adobe writer. 1. Format the Gantt chart the way you want it to look. 1a. If you do not want the right hand timeline, move that off the screen view. Do this by clicking and dragging the vertical line that separates the timeline from your left hand columns. 1b. If you want page breaks in ce... 30 Apr 2008 14:05
Is there a PowerPoint presentation add-in for Project 2007? There is an add-in for Project 2003 that creates a PowerPoint presentation directly from a project. Is there a similar add-in for Project 2007? Thanks, Al ... 16 May 2008 13:48
Graphical indicator for change to baseline start/finish I need to set up some graphical indicators to quickly show changes to the baseline start and/or finish date. Does anyone have these done, before I start writing the formulas myself. Thanks ... 30 Apr 2008 18:00
Visio Milestone Export I am using MSOP 2007. In previous versions there was an add in to export milestones to visio. Does this add in work for 2007? If so where can I find it? ... 30 Apr 2008 15:39
Actual Finish Date not updating in EVM Gnat Chart for completed ta I update actual performance within MSP using the Resource Usage View. I locate the resource then enter the actual hours the resource expended on the task. If the resource has completed the task but has remaining work, I zero out the remaining work. This closes the task, records the actual finish date and mar... 4 May 2008 11:54
Enterprise Reports In another deployment of Project Server 2007 with Sharepoint integration, I found another report listed under the report menu called "Enterprise Reports". I have tested installations and looked for additional components but can find no reference to this report. Is this a custom report that was added to the left... 30 Apr 2008 11:44
when I add resources my durations don't change - Why? My project is set up as fixed unit and effort driven. When I add resources to my tasks, the duration and the end date do not change. Why? ... 1 May 2008 11:24 |