MCTS Exam in Managing Projects with Microsoft Office Project2
Dale Howard [MVP] schrieb am 29.05.2008 07:13: ... To purchase the book, click on the following URL: http://www.projectserverbooks.com Dale, When attempting to connect to this address using Firefox, then I get an error, since the certificate cannot be verified using OCSP. Using IE, it works. I... 29 May 2008 04:23
% complete & actual finish date
I have created project with a phase having about 100 sub-tasks. I tried to track the actual start and actual finish of each task. However, it's only 2 tasks with 100% complete, the % complete of the phase was 23%. I noticed that the % complete did change if different actual finish date was input. In particularl... 29 May 2008 09:44
PV & BAC
Dear All, In the Ms. Project, I cannot find values for column PV [Planned Value of work schedule] and BAC [Budget At completion]. I want to add these two columns into the cost table but cannot find it in the available list. Please kindly advise. Regards, LG ... 29 May 2008 05:57
Need to capture REAL % complete of construction outputs
I need to track REAL % complete of tasks as of a status date, and need MS Project to recalculate remaining days based on this % complete. For example, if I have 10 days to build a wall, but after 2 days (status date) I am 50% finished building the wall, I want to capture: Actual Start Date % Complete = 50% Re... 29 May 2008 00:28
Header Height change
MS Project 2007: I need to decrease the header height when printing Gantt Chart, so that my project will appear on one page. I thought that page setup would allow this (Like Word), but I cannot find how to do it. Help would be appreciated. -- GeorgeO Jamestown, NC ... 28 May 2008 22:06
Cannot update resource calendar
I am using Enterprise Project Server 2007. I want to enter vacation days for my resources. When I select Tools --> change working time and select an individual's calendar I cannot change any days. Is there a permission that I need to have to do this? Or am I going about this is the correct way? thanks in a... 28 May 2008 18:11
Summary task Duration calculation error
I have a project that has started acting screwy and I can’t recall changing anything that should cause this. Summary tasks are no longer updating Duration to reflect sub task durations when they are changes. For instance I have a Summary duration that was 13.91 days and changes on of the subs to 16 days and the d... 28 May 2008 17:24
My total hours for each phase has a decimal.
My total hours for some phases has a decimal. Like 21.38. Any ideas? ... 28 May 2008 16:37
Work per day is wrong
Hi All, Resource is working on a job at 20% for 20 days = 4 days of work To me that should be 0.2 days of work per day but the Resource Usage view is showing 0.22d. This seems to be consistent across my project. Task Type is Fixed Duration. Calendar has been set to 7.4 hour day and 37 hour week. Start time etc... 29 May 2008 11:48
Timescale keeps changing
Hi All, Working in split view the timescale keeps changing from my preferred years/months (two tier) to quarters/months. I think it happens when I select a different view in the bottom pane. Can I make it stick at my preferred timescale? Regards. Bill. ... 28 May 2008 16:37