From: wasonamit on 14 May 2008 09:38 Hi, We created a Master Project in PS2007 and inserted sub-projects in it as read-only. But when we publish the Master Project it also publishes assignments updates of the sub-projects although these projects are read-only. We would like to avoid it. I was thinking of breaking the Link and Publishing it and re-establish the link after publishing the master. Any thoughts ?
From: wasonamit on 14 May 2008 09:53 Alright I broke the link and published the master now the resources gets an email that they are assigned to the Master. and then i cannot re-establish the link to the sub-project. Any help will be appreciated. "wasonamit" wrote: > Hi, > > We created a Master Project in PS2007 and inserted sub-projects in it as > read-only. > > But when we publish the Master Project it also publishes assignments updates > of the sub-projects although these projects are read-only. > > We would like to avoid it. > > I was thinking of breaking the Link and Publishing it and re-establish the > link after publishing the master. > > Any thoughts ? > >
From: MT_PMP on 15 May 2008 12:19 How are you "publishing" your Master Project? I use a "program level" project to link all of the projects I am working on together under one summary task and use that to speak with managers and stakeholders. When doing this, I use the "Insert Project" command under the Insert Menu and I have no issues whatsoever. If you provide a little more insight into your particular issue, I may be able to lead you in the right direction. -- If this response was helpful to you, please consider rating it! Thanks, MT_PMP "wasonamit" wrote: > Alright I broke the link and published the master now the resources gets an > email that they are assigned to the Master. > > and then i cannot re-establish the link to the sub-project. > > Any help will be appreciated. > > "wasonamit" wrote: > > > Hi, > > > > We created a Master Project in PS2007 and inserted sub-projects in it as > > read-only. > > > > But when we publish the Master Project it also publishes assignments updates > > of the sub-projects although these projects are read-only. > > > > We would like to avoid it. > > > > I was thinking of breaking the Link and Publishing it and re-establish the > > link after publishing the master. > > > > Any thoughts ? > > > >
From: wasonamit on 15 May 2008 14:10 I think Program Level and Master Projects are the same thing. Correct me if I am wrong. We have projects which are published in Project Server So I then Open a new project Insert > Projects > Retrieve the list.. > select the project Select Read-only... INSERT The new project in which we just embedded is the master project which we want to display in PWA > Project Center So we publish > but it also publishes the embedded project. "MT_PMP" wrote: > How are you "publishing" your Master Project? > > I use a "program level" project to link all of the projects I am working on > together under one summary task and use that to speak with managers and > stakeholders. When doing this, I use the "Insert Project" command under the > Insert Menu and I have no issues whatsoever. If you provide a little more > insight into your particular issue, I may be able to lead you in the right > direction. > -- > If this response was helpful to you, please consider rating it! > > Thanks, > MT_PMP > > > "wasonamit" wrote: > > > Alright I broke the link and published the master now the resources gets an > > email that they are assigned to the Master. > > > > and then i cannot re-establish the link to the sub-project. > > > > Any help will be appreciated. > > > > "wasonamit" wrote: > > > > > Hi, > > > > > > We created a Master Project in PS2007 and inserted sub-projects in it as > > > read-only. > > > > > > But when we publish the Master Project it also publishes assignments updates > > > of the sub-projects although these projects are read-only. > > > > > > We would like to avoid it. > > > > > > I was thinking of breaking the Link and Publishing it and re-establish the > > > link after publishing the master. > > > > > > Any thoughts ? > > > > > >
From: MT_PMP on 15 May 2008 16:19 That's what I was thinking you were doing. At this point, I can't give you anymore input because we have yet to deploy MS Project Server in our organization. We've had a demo of it and senior mgmt is considering the ROI. Hopefully, someone else can give you some feedback here. -- If this response was helpful to you, please consider rating it! Thanks, MT_PMP "wasonamit" wrote: > I think Program Level and Master Projects are the same thing. Correct me if I > am wrong. > > We have projects which are published in Project Server > > So I then Open a new project > Insert > Projects > Retrieve the list.. > select the project > > Select Read-only... INSERT > > The new project in which we just embedded is the master project which we > want to display in PWA > Project Center > So we publish > but it also publishes the embedded project. > > "MT_PMP" wrote: > > > How are you "publishing" your Master Project? > > > > I use a "program level" project to link all of the projects I am working on > > together under one summary task and use that to speak with managers and > > stakeholders. When doing this, I use the "Insert Project" command under the > > Insert Menu and I have no issues whatsoever. If you provide a little more > > insight into your particular issue, I may be able to lead you in the right > > direction. > > -- > > If this response was helpful to you, please consider rating it! > > > > Thanks, > > MT_PMP > > > > > > "wasonamit" wrote: > > > > > Alright I broke the link and published the master now the resources gets an > > > email that they are assigned to the Master. > > > > > > and then i cannot re-establish the link to the sub-project. > > > > > > Any help will be appreciated. > > > > > > "wasonamit" wrote: > > > > > > > Hi, > > > > > > > > We created a Master Project in PS2007 and inserted sub-projects in it as > > > > read-only. > > > > > > > > But when we publish the Master Project it also publishes assignments updates > > > > of the sub-projects although these projects are read-only. > > > > > > > > We would like to avoid it. > > > > > > > > I was thinking of breaking the Link and Publishing it and re-establish the > > > > link after publishing the master. > > > > > > > > Any thoughts ? > > > > > > > >
|