"JulieS" wrote:

> Hi Omar,
>
> Pardon me for jumping in.
>
> It appears as though you haven't saved the baseline for the successor task.
> Select the successor task and save the baseline (Tools>Tracking>Save
> baseline click "Selected task). You should now see the baseline Start and
> Finish fields populate with dates.
>
> Hope this helps. Let us know how you get along.
>
> Julie
>
> "omar" <omar(a)discussions.microsoft.com> wrote in message
> news:FD1B1FA6-4A4C-4204-BCB4-D3026BD08694(a)microsoft.com...
> > Ok here is what I am trying to do:
> > I have two projects and I linked a task from one project to the other. In
> > the predecessor, I changed the duration of the project and in turn it
> > updated
> > the finish date. I manually saved the baselines so that everything gets
> > updated. On the Successor, only the start date and finish date gets
> > updated
> > but the baselines remains NA. Why is it like that?
> >
> > thank you
> >
> > "Rod Gill" wrote:
> >
> >> So what are you expecting to see and what isn't happening. Please explain
> >> more what your question is about and how to reproduce it..
> >>
> >> --
> >>
> >> Rod Gill
> >> Project MVP
> >> Visit www.msproject-systems.com for Project Companion Tools and more
> >>
> >>
> >> "omar" <omar(a)discussions.microsoft.com> wrote in message
> >> news:DEACC6A6-D3D1-4D39-ABE0-5FCF699697CC(a)microsoft.com...
> >> > When tasks between two projects, why doesnt all the custom fields show?
> >> > (I
> >> > mean some custom field stays NA)
> >>
> >>
> >>
>
>
>
From: "JulieS" <passport6847 at maine dot rr dot on
Hi Patricia,

You have posted your question to a newsgroup for Microsoft Project. Try
posting to a newsgroup for the email program you are using such as Outlook
or Outlook Express.

Julie
"Patricia" <Patricia(a)discussions.microsoft.com> wrote in message
news:51444ADA-DB08-4C0F-9BAB-E7C81E10D051(a)microsoft.com...
> How can I recall just one email that I sent to many?
>
> "JulieS" wrote:
>
>> Hi Omar,
>>
>> Pardon me for jumping in.
>>
>> It appears as though you haven't saved the baseline for the successor
>> task.
>> Select the successor task and save the baseline (Tools>Tracking>Save
>> baseline click "Selected task). You should now see the baseline Start
>> and
>> Finish fields populate with dates.
>>
>> Hope this helps. Let us know how you get along.
>>
>> Julie
>>
>> "omar" <omar(a)discussions.microsoft.com> wrote in message
>> news:FD1B1FA6-4A4C-4204-BCB4-D3026BD08694(a)microsoft.com...
>> > Ok here is what I am trying to do:
>> > I have two projects and I linked a task from one project to the other.
>> > In
>> > the predecessor, I changed the duration of the project and in turn it
>> > updated
>> > the finish date. I manually saved the baselines so that everything gets
>> > updated. On the Successor, only the start date and finish date gets
>> > updated
>> > but the baselines remains NA. Why is it like that?
>> >
>> > thank you
>> >
>> > "Rod Gill" wrote:
>> >
>> >> So what are you expecting to see and what isn't happening. Please
>> >> explain
>> >> more what your question is about and how to reproduce it..
>> >>
>> >> --
>> >>
>> >> Rod Gill
>> >> Project MVP
>> >> Visit www.msproject-systems.com for Project Companion Tools and more
>> >>
>> >>
>> >> "omar" <omar(a)discussions.microsoft.com> wrote in message
>> >> news:DEACC6A6-D3D1-4D39-ABE0-5FCF699697CC(a)microsoft.com...
>> >> > When tasks between two projects, why doesnt all the custom fields
>> >> > show?
>> >> > (I
>> >> > mean some custom field stays NA)
>> >>
>> >>
>> >>
>>
>>
>>