From: FreeWill on 16 Nov 2005 17:25 I am looking for a way to show a rolled up milestone only to the imediate level. In other words, I want to exclude some milestones that get rolled up to the top level. Is there a way to do this or will I be forced to rollup milestones all the way to the top level?
From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot on 17 Nov 2005 02:29 Hi, No Problem For all parents but the immediate one, cross out "Show Rolled Up Gantt Bars" in Task Information, General. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "FreeWill" <FreeWill(a)discussions.microsoft.com> schreef in bericht news:2ED98008-82C3-4BC0-BD7B-BA70167F9D45(a)microsoft.com... > I am looking for a way to show a rolled up milestone only to the imediate > level. In other words, I want to exclude some milestones that get rolled up > to the top level. Is there a way to do this or will I be forced to rollup > milestones all the way to the top level?
From: FreeWill on 17 Nov 2005 10:51 Thanks for the sugestion, but it dosent seem to work. Not sure what I am doing wrong. Also, wouldn't your solution cause all Milestones to not roll up to the parent level that I crossed out "Show Rolled Up Gantt Bars"? I would like to select which milestones that rollup to the top level. Thanks for your help, Will Visser "Jan De Messemaeker" wrote: > Hi, > > No Problem > For all parents but the immediate one, cross out "Show Rolled Up Gantt Bars" > in Task Information, General. > HTH > > -- > Jan De Messemaeker > Microsoft Project Most Valuable Professional > http://users.online.be/prom-ade/ > +32-495-300 620 > "FreeWill" <FreeWill(a)discussions.microsoft.com> schreef in bericht > news:2ED98008-82C3-4BC0-BD7B-BA70167F9D45(a)microsoft.com... > > I am looking for a way to show a rolled up milestone only to the imediate > > level. In other words, I want to exclude some milestones that get rolled > up > > to the top level. Is there a way to do this or will I be forced to rollup > > milestones all the way to the top level? > > >
From: FreeWill on 17 Nov 2005 14:12 I think I see the part of the problem. Your sugestion will work if I am in the Normal Gantt view. The problem is that I have set up this project as a multiple gantt bar view. I did this so that I could track different types of dates for the same task. When using this view all milestones rollup regardless of whether I cross out the "Show Rolled up gantt bars" box. Thanks for your help, Will Visser "FreeWill" wrote: > Thanks for the sugestion, but it dosent seem to work. Not sure what I am > doing wrong. Also, wouldn't your solution cause all Milestones to not roll > up to the parent level that I crossed out "Show Rolled Up Gantt Bars"? I > would like to select which milestones that rollup to the top level. > > Thanks for your help, > Will Visser > > "Jan De Messemaeker" wrote: > > > Hi, > > > > No Problem > > For all parents but the immediate one, cross out "Show Rolled Up Gantt Bars" > > in Task Information, General. > > HTH > > > > -- > > Jan De Messemaeker > > Microsoft Project Most Valuable Professional > > http://users.online.be/prom-ade/ > > +32-495-300 620 > > "FreeWill" <FreeWill(a)discussions.microsoft.com> schreef in bericht > > news:2ED98008-82C3-4BC0-BD7B-BA70167F9D45(a)microsoft.com... > > > I am looking for a way to show a rolled up milestone only to the imediate > > > level. In other words, I want to exclude some milestones that get rolled > > up > > > to the top level. Is there a way to do this or will I be forced to rollup > > > milestones all the way to the top level? > > > > > >
From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot on 17 Nov 2005 13:15 Hi, You can only stop the rolling up at summary task level. You cannot tell a milestone to rollup only one level. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional http://users.online.be/prom-ade/ +32-495-300 620 "FreeWill" <FreeWill(a)discussions.microsoft.com> schreef in bericht news:5EB62769-9755-4CB1-8C77-3513F08CB2F2(a)microsoft.com... > Thanks for the sugestion, but it dosent seem to work. Not sure what I am > doing wrong. Also, wouldn't your solution cause all Milestones to not roll > up to the parent level that I crossed out "Show Rolled Up Gantt Bars"? I > would like to select which milestones that rollup to the top level. > > Thanks for your help, > Will Visser > > "Jan De Messemaeker" wrote: > > > Hi, > > > > No Problem > > For all parents but the immediate one, cross out "Show Rolled Up Gantt Bars" > > in Task Information, General. > > HTH > > > > -- > > Jan De Messemaeker > > Microsoft Project Most Valuable Professional > > http://users.online.be/prom-ade/ > > +32-495-300 620 > > "FreeWill" <FreeWill(a)discussions.microsoft.com> schreef in bericht > > news:2ED98008-82C3-4BC0-BD7B-BA70167F9D45(a)microsoft.com... > > > I am looking for a way to show a rolled up milestone only to the imediate > > > level. In other words, I want to exclude some milestones that get rolled > > up > > > to the top level. Is there a way to do this or will I be forced to rollup > > > milestones all the way to the top level? > > > > > >
|