From: Earl on 15 May 2008 17:27 I'm a relatively new user to MS Project 2007, but have created a nice Gantt Chart for my project complete with Start and Finish dates. I've inserted Actual Start and Actual Finish columns into my chart, but whenever I try to updated the Actual Start date for a task, it changes the Start date. For example, if my Start date for a task was April 1, but I enter the Actual Start date as April 2, my Start date changes to April 2. Note: The Start date is actually more like a scheduled start date, and it seems like tracking my progress would be difficult if the Start and Actual Start dates match up. What am I missing? Thanks. Earl
|