|
Prev: 2 Questions - New to Project
Next: MSP 2000 - how to display current day when opening a project file?
From: CB on 9 May 2008 09:47 I am using MSOP 2007 standard. I have two tasks in particular in my schedule. Task 3 is linked to task 2. Task 2 is 80% complete, started on 4/1/08, Task 3 is 10% complete and started on 4/29/08. I want to reschedule my remaining work. I go to Tools-Tracking-Update Project-I select Reschedule uncomplet work to start after 5/7/08 For Entire project. When this is selected only task 2 is updated. I can go through this sequence again and task 3 is finally updated. Why? Am I missing something here? I would expect project to go through each task and reschedule the remaining work based on the predecessors. For instance if task 2s new completion date is June 23 and task 3 is linked to task 2 with a FS relationship and has 20 hours remaining, I would expect project to split task 3 leaving the actuals in tact and reschedule the remaining 20 hours to start June 24th. Any ideas?
From: salgud on 9 May 2008 12:54
On Fri, 9 May 2008 06:47:00 -0700, CB wrote: > I am using MSOP 2007 standard. I have two tasks in particular in my > schedule. Task 3 is linked to task 2. Task 2 is 80% complete, started on > 4/1/08, Task 3 is 10% complete and started on 4/29/08. I want to reschedule > my remaining work. I go to Tools-Tracking-Update Project-I select Reschedule > uncomplet work to start after 5/7/08 For Entire project. When this is > selected only task 2 is updated. I can go through this sequence again and > task 3 is finally updated. Why? Am I missing something here? I would > expect project to go through each task and reschedule the remaining work > based on the predecessors. For instance if task 2s new completion date is > June 23 and task 3 is linked to task 2 with a FS relationship and has 20 > hours remaining, I would expect project to split task 3 leaving the actuals > in tact and reschedule the remaining 20 hours to start June 24th. > Any ideas? If task 3 is a successor to task 2, then it can't start until task 2 is complete. That's what that means. If task 2 is only 80% complete, the logic you've given Project says task 3 can't start yet. Maybe what you want is to overlap the tasks using lead time (negative lag time) to show their real relationship. Hope this helps in your world. |