From: Christoph Muelder Christoph on 15 May 2008 16:17 Hi Jan, the problem with deadlines not being used for slack calculation has been resolved in a hotfix and is included in SP1. It works again now. You can change back to your old recommendations - as I did :-) Best regards Christoph "Jan De Messemaeker" wrote: > Hi Julie, > > Right you are; it caused me to review completely the process I recommend to > customers (and use myself). > I base decisions on Total Slack, and in 2007 that indeed does not take into > account deadlines. Shame. > So it's back to Prpoejct 98 methods: instead of a deadline set a Must > constrained milesone and links your final task to that. > To me deadline has become almost useless. > > -- > Jan De Messemaeker > Microsoft Project Most Valuable Professional > +32 495 300 620 > For availability check: > http://users.online.be/prom-ade/Calendar.pdf > "JulieS" <JulieS(a)discussions.microsoft.com> wrote in message > news:Oi9bsaCkIHA.2396(a)TK2MSFTNGP05.phx.gbl... > > Hello Jan, > > > > The OP doesn't note what version of project is in use, but I did notice > > that setting deadlines in Project 2007 does not affect late start and late > > finish as it does in earlier releases. > > > > Julie > > > > "Jan De Messemaeker" <janremovethis(a)prom-ade.be> wrote in message > > news:e1nHbO9jIHA.4076(a)TK2MSFTNGP05.phx.gbl... > >> Hi, > >> > >> Don't the fields late start and late finish give you what you want? > >> -- > >> Jan De Messemaeker > >> Microsoft Project Most Valuable Professional > >> +32 495 300 620 > >> For availability check: > >> http://users.online.be/prom-ade/Calendar.pdf > > <snip> > > > > >
|
Pages: 1 Prev: Help with understanding leveling... MS Project 2003 Next: Project 2007 locks Project 2003 |