From: Damian on 15 May 2008 06:17 Hi, Does anyone know how to make Project Statistics (Project->Project Information->Statistics) use Baseline1 rather than Baseline? I'm using Project Standard 2003. Thanks Damian.
From: JulieS on 17 May 2008 13:32 Hello Damian, Sorry, no. You could copy your Baseline data into a spare Baseline (Baseline10 for example) and then copy Baseline1 into Baseline. See Tools > Tracking, Save Baseline and see the interim plan options. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "Damian" <damianhelme(a)gmail.com> wrote in message news:c39a2a88-faae-4386-9e44-50e63462a4b4(a)m45g2000hsb.googlegroups.com... > Hi, > > Does anyone know how to make Project Statistics (Project->Project > Information->Statistics) use Baseline1 rather than Baseline? > > I'm using Project Standard 2003. > > Thanks > > Damian.
|