From: Damian on
Hi,

Does anyone know how to make Project Statistics (Project->Project
Information->Statistics) use Baseline1 rather than Baseline?

I'm using Project Standard 2003.

Thanks

Damian.
From: JulieS on
Hello Damian,

Sorry, no. You could copy your Baseline data into a spare Baseline
(Baseline10 for example) and then copy Baseline1 into Baseline. See
Tools > Tracking, Save Baseline and see the interim plan options.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project