|
Prev: forecast %complete
Next: "Operation Failed"
From: nzeches on 28 Apr 2008 09:10 Hello folks I have a project with tenths of items to ship to a site before work can start. I currently maintain a list of milestones with suppliers deliveries (EXW), however I have to add to the delivery date the time for shipment, which is a constant for my project. There are several ways to do it, eg for 35 days of transport: - either I add one 35 days "transport" task (although this is not a task of my project) as a successor to each delivery milestone (~70 tasks) with a successor milestone "item X available on site" - or I create a successor milestone to each delivery with a "FS +35days" link for the final delivery to site Let us consider that transport is now 55days ; I have to update manually ~70 tasks scattered across my 500+ ytasks project to reflect the change (hoping not to miss one). How could I create a "constant" called "shipment time" which I could use in each task duration or link, that I could easily change once and for all ? Thanks in advance for your advice -- NZ
From: John on 28 Apr 2008 11:09 In article <4bfbe76d-ceea-4d79-b1d4-ded500689729(a)c65g2000hsa.googlegroups.com>, nzeches(a)googlemail.com wrote: > Hello folks > > I have a project with tenths of items to ship to a site before work > can start. > I currently maintain a list of milestones with suppliers deliveries > (EXW), however I have to add to the delivery date the time for > shipment, which is a constant for my project. > > There are several ways to do it, eg for 35 days of transport: > - either I add one 35 days "transport" task (although this is not a > task of my project) as a successor to each delivery milestone (~70 > tasks) with a successor milestone "item X available on site" > - or I create a successor milestone to each delivery with a "FS > +35days" link for the final delivery to site > > Let us consider that transport is now 55days ; I have to update > manually ~70 tasks scattered across my 500+ ytasks project to reflect > the change (hoping not to miss one). > How could I create a "constant" called "shipment time" which I could > use in each task duration or link, that I could easily change once and > for all ? > > Thanks in advance for your advice > -- > NZ NZ, The best way to do this is with VBA - that's really the only way (I can think of) to create the "constant" you desire. Another approach that doesn't require VBA would be to create a filter that looks for "35d" in the Predecessor field or "transport" in the Task Name field, depending on which transport time approach you choose. Either filter will single out just those tasks with the transport time. It will be a little more tedious to update all the predecessor values, but at least they are all together. If the transport is a separate task for each deliverable, it is very easy to change the Duration field using fill down. Hope this helps. John Project MVP
From: Trevor Rabey on 28 Apr 2008 11:42 If you filter or group on the tasks you want, it will make all the tasks you are interested in make a list with them all together and then it is easy to type in the top cell and fill down the rest. Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au <nzeches(a)googlemail.com> wrote in message news:4bfbe76d-ceea-4d79-b1d4-ded500689729(a)c65g2000hsa.googlegroups.com... > Hello folks > > I have a project with tenths of items to ship to a site before work > can start. > I currently maintain a list of milestones with suppliers deliveries > (EXW), however I have to add to the delivery date the time for > shipment, which is a constant for my project. > > There are several ways to do it, eg for 35 days of transport: > - either I add one 35 days "transport" task (although this is not a > task of my project) as a successor to each delivery milestone (~70 > tasks) with a successor milestone "item X available on site" > - or I create a successor milestone to each delivery with a "FS > +35days" link for the final delivery to site > > Let us consider that transport is now 55days ; I have to update > manually ~70 tasks scattered across my 500+ ytasks project to reflect > the change (hoping not to miss one). > How could I create a "constant" called "shipment time" which I could > use in each task duration or link, that I could easily change once and > for all ? > > Thanks in advance for your advice > -- > NZ
From: Dean C on 28 Apr 2008 13:53 The problem you have with using a constant that may change, is the ability to have pre-change values stay at 35 days while the post-change values switch to 55 days. If the duration of a completed task is changed, the actual finish date will change. I suggest adding your "transport" tasks with the 35 day duration. When the shipping time switches to 55 days, filter for incomplete transport tasks, select the duration column, type 55 {Enter} then Ctrl-D (fill down) . "nzeches(a)googlemail.com" wrote: > Hello folks > > I have a project with tenths of items to ship to a site before work > can start. > I currently maintain a list of milestones with suppliers deliveries > (EXW), however I have to add to the delivery date the time for > shipment, which is a constant for my project. > > There are several ways to do it, eg for 35 days of transport: > - either I add one 35 days "transport" task (although this is not a > task of my project) as a successor to each delivery milestone (~70 > tasks) with a successor milestone "item X available on site" > - or I create a successor milestone to each delivery with a "FS > +35days" link for the final delivery to site > > Let us consider that transport is now 55days ; I have to update > manually ~70 tasks scattered across my 500+ ytasks project to reflect > the change (hoping not to miss one). > How could I create a "constant" called "shipment time" which I could > use in each task duration or link, that I could easily change once and > for all ? > > Thanks in advance for your advice > -- > NZ >
|
Pages: 1 Prev: forecast %complete Next: "Operation Failed" |