Prev: How to disable a task without deleting it from MS PROJECT Template
Next: baseline selected tasks
From: Paul C Paul on 14 May 2008 17:00 Where is the pert calculate button in project 2003 professional edition? Tried right clicking in all tool bars and could not find it.
From: JulieS on 14 May 2008 17:04 Hi Paul, The PERT Analysis toolbar has the Calculate PERT button. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "Paul C" <Paul C(a)discussions.microsoft.com> wrote in message news:AF703790-2090-4A7C-A258-C05809CC89F5(a)microsoft.com... > Where is the pert calculate button in project 2003 professional > edition? > Tried right clicking in all tool bars and could not find it.
From: Paul C on 14 May 2008 17:13 Where or how do I open the Pert Analysis toolbar? Paul C "JulieS" wrote: > Hi Paul, > > The PERT Analysis toolbar has the Calculate PERT button. > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional information > about Microsoft Project > > > "Paul C" <Paul C(a)discussions.microsoft.com> wrote in message > news:AF703790-2090-4A7C-A258-C05809CC89F5(a)microsoft.com... > > Where is the pert calculate button in project 2003 professional > > edition? > > Tried right clicking in all tool bars and could not find it. > > >
From: JulieS on 14 May 2008 17:32 Hi Paul, View > Toolbars > Pert Analysis. Julie "Paul C" <PaulC(a)discussions.microsoft.com> wrote in message news:5445C240-2FD3-4086-A1E8-B1E8676A7E04(a)microsoft.com... > Where or how do I open the Pert Analysis toolbar? > > Paul C > > "JulieS" wrote: > >> Hi Paul, >> >> The PERT Analysis toolbar has the Calculate PERT button. >> >> I hope this helps. Let us know how you get along. >> >> Julie >> Project MVP >> >> Visit http://project.mvps.org/ for the FAQs and additional >> information >> about Microsoft Project >> >> >> "Paul C" <Paul C(a)discussions.microsoft.com> wrote in message >> news:AF703790-2090-4A7C-A258-C05809CC89F5(a)microsoft.com... >> > Where is the pert calculate button in project 2003 professional >> > edition? >> > Tried right clicking in all tool bars and could not find it. >> >> >>
From: salgud on 14 May 2008 17:33 On Wed, 14 May 2008 14:13:01 -0700, Paul C wrote: > Where or how do I open the Pert Analysis toolbar? > > Paul C > > "JulieS" wrote: > >> Hi Paul, >> >> The PERT Analysis toolbar has the Calculate PERT button. >> >> I hope this helps. Let us know how you get along. >> >> Julie >> Project MVP >> >> Visit http://project.mvps.org/ for the FAQs and additional information >> about Microsoft Project >> >> >> "Paul C" <Paul C(a)discussions.microsoft.com> wrote in message >> news:AF703790-2090-4A7C-A258-C05809CC89F5(a)microsoft.com... >>> Where is the pert calculate button in project 2003 professional >>> edition? >>> Tried right clicking in all tool bars and could not find it. >> >> >> Right click on any toolbar, select "PERT Analysis" from the list to activate the toolbar. BTW, you may not have heard, PERT 3 duration scheduling has been largely discredited due to the fact that it's statistically unsound. If you want do the same basic thing in a statistically sound way, use Monte Carlo analysis. There is third party software which will integrate with Project to do this. I imagine you can still find it by googling. Hope this helps in your world.
|
Pages: 1 Prev: How to disable a task without deleting it from MS PROJECT Template Next: baseline selected tasks |