From: Dennis on
Hello

I want for one recourse a workdag from 10hours. I want to do it so that
i give up 1 day duration but from 8 workhours and 2 hours overtime. For
the overtime i can give up fixt cost at the resource. I cant get it don
to make one day from 10 hours. I made a new callender from 08:00 -
19:00 and link tthe calender to the resource.

Now i see at work 8hours and nothing more?? I want to see by duration 1
day, by work 8hours and by overtime 2hours. Then the costs of the
workhours and the costs of the overtime.

I have all the collumns but the dont have any information.

What do i wrong??

Thanks

From: JulieS on
Hello Dennis,

Sorry, Project will not automatically assign overtime, you must do
that yourself. If you want an 8 hour (1 day) duration task to be
worked on for a total of 10 hours (8 regular and 2 OT), you'll need to
specify that when you assign the resource.

I suggest working with the Task Form at the bottom of your screen
formatted to show Resource Work. To show the task form choose Window
> Split from a Gantt chart. Once you have the Task Form visible at
the lower pane, click in the Task form, click your right mouse button
to show the shortcut menu and select Resource Work.

Create the 1 day duration task. Click in the task form and select the
resource, in the Work field enter 10, in the OVT work field enter 2
click OK.

The resource is now assigned to a one day (8 hour) duration task
accomplishing 10 hours of work. The 2 hours OT should be at the OT
rate field you set in the Resource Sheet.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project



<Dennis> wrote in message
news:48162841$0$3665$e4fe514c(a)dreader31.news.xs4all.nl...
> Hello
>
> I want for one recourse a workdag from 10hours. I want to do it so
> that i give up 1 day duration but from 8 workhours and 2 hours
> overtime. For the overtime i can give up fixt cost at the resource.
> I cant get it don to make one day from 10 hours. I made a new
> callender from 08:00 - 19:00 and link tthe calender to the resource.
>
> Now i see at work 8hours and nothing more?? I want to see by
> duration 1 day, by work 8hours and by overtime 2hours. Then the
> costs of the workhours and the costs of the overtime.
>
> I have all the collumns but the dont have any information.
>
> What do i wrong??
>
> Thanks
>


From: Jeroen on
Ok it worked. Thanks

> Hello Dennis,
>
> Sorry, Project will not automatically assign overtime, you must do
> that yourself. If you want an 8 hour (1 day) duration task to be
> worked on for a total of 10 hours (8 regular and 2 OT), you'll need to
> specify that when you assign the resource.
>
> I suggest working with the Task Form at the bottom of your screen
> formatted to show Resource Work. To show the task form choose Window
> > Split from a Gantt chart. Once you have the Task Form visible at
> the lower pane, click in the Task form, click your right mouse button
> to show the shortcut menu and select Resource Work.
>
> Create the 1 day duration task. Click in the task form and select the
> resource, in the Work field enter 10, in the OVT work field enter 2
> click OK.
>
> The resource is now assigned to a one day (8 hour) duration task
> accomplishing 10 hours of work. The 2 hours OT should be at the OT
> rate field you set in the Resource Sheet.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
>
>
> <Dennis> wrote in message
> news:48162841$0$3665$e4fe514c(a)dreader31.news.xs4all.nl...
>> Hello
>>
>> I want for one recourse a workdag from 10hours. I want to do it so
>> that i give up 1 day duration but from 8 workhours and 2 hours
>> overtime. For the overtime i can give up fixt cost at the resource.
>> I cant get it don to make one day from 10 hours. I made a new
>> callender from 08:00 - 19:00 and link tthe calender to the resource.
>>
>> Now i see at work 8hours and nothing more?? I want to see by
>> duration 1 day, by work 8hours and by overtime 2hours. Then the
>> costs of the workhours and the costs of the overtime.
>>
>> I have all the collumns but the dont have any information.
>>
>> What do i wrong??
>>
>> Thanks


From: JulieS on
You're welcome.

Julie
<Jeroen> wrote in message
news:4820a4c3$0$26899$e4fe514c(a)dreader30.news.xs4all.nl...
> Ok it worked. Thanks
<snip>


 | 