From: Lee Colgate on
Daniela makes an excellent point, though. It is often vital to highlight in
a project plan (particularly when you're dependent on, for example, a client)
to be able to indicate VERY clearly where such dependencies exist. While in
Proj Man practice an external task is something that exists in a different
project, are there plans to make it possible to apply a different format
where External Resource is relied on for delivery of a task automatically?

And does the functionality your link points to (which is detailed for MSP
2000) also work in later versions? I have 2007.
--
Lee


"Jan De Messemaeker" wrote:

> Hi Daniela,
>
> If you only want clarity by coloring some tasks differently, that's no
> problem.
> See
> http://www.mvps.org/project/faqs.htm
>
> Faq 31. Customizing Task Bars
>
> HTH
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> http://users.online.be/prom-ade/
> +32-495-300 620
> "Guidho" <nospam(a)mybox> schreef in bericht
> news:usVadN2aFHA.1088(a)TK2MSFTNGP14.phx.gbl...
> > An external task is a task which resides in another project plan.
> > For example: if you insert a project plan into your existing plan
> > (insert -> project) and you link a tsak from your original plan with a
> > task from the inserted plan, the task from your existing plan will show
> > up as an external task in the original file of the inserted plan.
> >
> > Be carefull, physically linking project plans is not a best pratice...
> >
> > Regards,
> > Guidho
> >
> > Dariela wrote:
> > > In the legend of Gantt chart appears "external task". How can I make a
> > > "normal" task to be external and this to appear in the schedule as
> different
> > > (colour) from the others?
> > >
> > > Thank you,
> > > Dariela
>
>
>
From: JulieS on
Hello Lee,

Yes, FAQ 31 works in Project 2007 as well.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

"Lee Colgate" <LeeColgate(a)discussions.microsoft.com> wrote in message
news:7FC0678F-3F7C-40E8-9B4B-CC25C49C3FDC(a)microsoft.com...
> Daniela makes an excellent point, though. It is often vital to
> highlight in
> a project plan (particularly when you're dependent on, for example,
> a client)
> to be able to indicate VERY clearly where such dependencies exist.
> While in
> Proj Man practice an external task is something that exists in a
> different
> project, are there plans to make it possible to apply a different
> format
> where External Resource is relied on for delivery of a task
> automatically?
>
> And does the functionality your link points to (which is detailed
> for MSP
> 2000) also work in later versions? I have 2007.
> --
> Lee
>
>
> "Jan De Messemaeker" wrote:
>
>> Hi Daniela,
>>
>> If you only want clarity by coloring some tasks differently, that's
>> no
>> problem.
>> See
>> http://www.mvps.org/project/faqs.htm
>>
>> Faq 31. Customizing Task Bars
>>
>> HTH
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> http://users.online.be/prom-ade/
>> +32-495-300 620
>> "Guidho" <nospam(a)mybox> schreef in bericht
>> news:usVadN2aFHA.1088(a)TK2MSFTNGP14.phx.gbl...
>> > An external task is a task which resides in another project plan.
>> > For example: if you insert a project plan into your existing plan
>> > (insert -> project) and you link a tsak from your original plan
>> > with a
>> > task from the inserted plan, the task from your existing plan
>> > will show
>> > up as an external task in the original file of the inserted plan.
>> >
>> > Be carefull, physically linking project plans is not a best
>> > pratice...
>> >
>> > Regards,
>> > Guidho
>> >
>> > Dariela wrote:
>> > > In the legend of Gantt chart appears "external task". How can I
>> > > make a
>> > > "normal" task to be external and this to appear in the schedule
>> > > as
>> different
>> > > (colour) from the others?
>> > >
>> > > Thank you,
>> > > Dariela
>>
>>
>>