|
Prev: Indicator on resource availability, in MS Project Professional
Next: Solution Starter: Scrum for Project 2003
From: D Pingger on 19 May 2008 02:09 WHOA!!!!!! Thanks for nosing in, John!!!!! What a simple answer! Yes, I made the fix and it now works. I only had the column formated as a number; changed it to a % format and everything works. This board rocks because of experts like Julie and You! Thanks again for caring about users problems like me. DPingger "John" wrote: > In article <6E032E06-8609-433D-AEB6-A8E12ABB654E(a)microsoft.com>, > D Pingger <DPingger(a)discussions.microsoft.com> wrote: > > > Hi JulieS, > > > > I tried just importing the % complete field (deleted the other two fields > > from the file) and it still wouldn't do it. Hmmmmm. I'm way stumped now. > > > > Help!?!?!?!?! > > > > DPingger > > DPingger, > Pardon me for nosing in. How is the percent complete value expressed in > Excel? If it is just a number, (i.e. 60 for 60%), Project will not > recognize that format and will import 0%. However, if it is expressed in > Excel as a percent or decimal, (i.e. 60% or .6), then it will be > imported. > > John > Project MVP > > > > "JulieS" wrote: > > > > > Hi D Pingger, > > > > > > What other data are you importing? It may be possible that you have > > > data being imported which conflicts with the % complete. For example, > > > if you try to import % complete but also import actual and remaining > > > duration, the percent complete field is going to be recalculated by > > > the actual and remaining duration values. > > > > > > Percent complete = (actual duration/duration)*100 > > > > > > I hope this helps. Let us know how you get along. > > > > > > Julie > > > Project MVP > > > > > > Visit http://project.mvps.org/ for the FAQs and additional information > > > about Microsoft Project > > > > > > "D Pingger" <DPingger(a)discussions.microsoft.com> wrote in message > > > news:0F2EC29E-AE67-4A1D-8CAF-3F7ECED8E6B4(a)microsoft.com... > > > > In 2003, I'm updating data using an excel spreadsheet but for some > > > > reason, > > > > the %complete value doesn't import back in. Is there something I'm > > > > missing? > > > > > > > > I use the import wizard and mapping. > > > > > > > > Help! > > > > > > > > TIA > > > > DPingger > > > > > > > > > >
From: JulieS on 19 May 2008 08:16 You're most welcome D Pingger. And thanks for the "nose" in John -- great catch :-) Julie "D Pingger" <DPingger(a)discussions.microsoft.com> wrote in message news:D8355C0A-167B-4DFB-9F8E-3C45001E394E(a)microsoft.com... > WHOA!!!!!! > > Thanks for nosing in, John!!!!! > > What a simple answer! Yes, I made the fix and it now works. I only > had the > column formated as a number; changed it to a % format and everything > works. > > This board rocks because of experts like Julie and You! > > Thanks again for caring about users problems like me. > > DPingger > > "John" wrote: > >> In article <6E032E06-8609-433D-AEB6-A8E12ABB654E(a)microsoft.com>, >> D Pingger <DPingger(a)discussions.microsoft.com> wrote: >> >> > Hi JulieS, >> > >> > I tried just importing the % complete field (deleted the other >> > two fields >> > from the file) and it still wouldn't do it. Hmmmmm. I'm way >> > stumped now. >> > >> > Help!?!?!?!?! >> > >> > DPingger >> >> DPingger, >> Pardon me for nosing in. How is the percent complete value >> expressed in >> Excel? If it is just a number, (i.e. 60 for 60%), Project will not >> recognize that format and will import 0%. However, if it is >> expressed in >> Excel as a percent or decimal, (i.e. 60% or .6), then it will be >> imported. >> >> John >> Project MVP >> > >> > "JulieS" wrote: >> > >> > > Hi D Pingger, >> > > >> > > What other data are you importing? It may be possible that you >> > > have >> > > data being imported which conflicts with the % complete. For >> > > example, >> > > if you try to import % complete but also import actual and >> > > remaining >> > > duration, the percent complete field is going to be >> > > recalculated by >> > > the actual and remaining duration values. >> > > >> > > Percent complete = (actual duration/duration)*100 >> > > >> > > I hope this helps. Let us know how you get along. >> > > >> > > Julie >> > > Project MVP >> > > >> > > Visit http://project.mvps.org/ for the FAQs and additional >> > > information >> > > about Microsoft Project >> > > >> > > "D Pingger" <DPingger(a)discussions.microsoft.com> wrote in >> > > message >> > > news:0F2EC29E-AE67-4A1D-8CAF-3F7ECED8E6B4(a)microsoft.com... >> > > > In 2003, I'm updating data using an excel spreadsheet but for >> > > > some >> > > > reason, >> > > > the %complete value doesn't import back in. Is there >> > > > something I'm >> > > > missing? >> > > > >> > > > I use the import wizard and mapping. >> > > > >> > > > Help! >> > > > >> > > > TIA >> > > > DPingger >> > > >> > > >> > > >>
From: John on 19 May 2008 10:46 In article <D8355C0A-167B-4DFB-9F8E-3C45001E394E(a)microsoft.com>, D Pingger <DPingger(a)discussions.microsoft.com> wrote: > WHOA!!!!!! > > Thanks for nosing in, John!!!!! > > What a simple answer! Yes, I made the fix and it now works. I only had the > column formated as a number; changed it to a % format and everything works. > > This board rocks because of experts like Julie and You! > > Thanks again for caring about users problems like me. > > DPingger D Pingger, Let's see, we band together as MVPs to help the users and you say that we rock. I guess that makes us a rock band :-) You're welcome. Sometimes I just get lucky. John Project MVP > > "John" wrote: > > > In article <6E032E06-8609-433D-AEB6-A8E12ABB654E(a)microsoft.com>, > > D Pingger <DPingger(a)discussions.microsoft.com> wrote: > > > > > Hi JulieS, > > > > > > I tried just importing the % complete field (deleted the other two fields > > > from the file) and it still wouldn't do it. Hmmmmm. I'm way stumped now. > > > > > > Help!?!?!?!?! > > > > > > DPingger > > > > DPingger, > > Pardon me for nosing in. How is the percent complete value expressed in > > Excel? If it is just a number, (i.e. 60 for 60%), Project will not > > recognize that format and will import 0%. However, if it is expressed in > > Excel as a percent or decimal, (i.e. 60% or .6), then it will be > > imported. > > > > John > > Project MVP > > > > > > "JulieS" wrote: > > > > > > > Hi D Pingger, > > > > > > > > What other data are you importing? It may be possible that you have > > > > data being imported which conflicts with the % complete. For example, > > > > if you try to import % complete but also import actual and remaining > > > > duration, the percent complete field is going to be recalculated by > > > > the actual and remaining duration values. > > > > > > > > Percent complete = (actual duration/duration)*100 > > > > > > > > I hope this helps. Let us know how you get along. > > > > > > > > Julie > > > > Project MVP > > > > > > > > Visit http://project.mvps.org/ for the FAQs and additional information > > > > about Microsoft Project > > > > > > > > "D Pingger" <DPingger(a)discussions.microsoft.com> wrote in message > > > > news:0F2EC29E-AE67-4A1D-8CAF-3F7ECED8E6B4(a)microsoft.com... > > > > > In 2003, I'm updating data using an excel spreadsheet but for some > > > > > reason, > > > > > the %complete value doesn't import back in. Is there something I'm > > > > > missing? > > > > > > > > > > I use the import wizard and mapping. > > > > > > > > > > Help! > > > > > > > > > > TIA > > > > > DPingger > > > > > > > > > > > > > >
First
|
Prev
|
Pages: 1 2 Prev: Indicator on resource availability, in MS Project Professional Next: Solution Starter: Scrum for Project 2003 |