From: D Pingger on
In 2003, I'm updating data using an excel spreadsheet but for some reason,
the %complete value doesn't import back in. Is there something I'm missing?

I use the import wizard and mapping.

Help!

TIA
DPingger
From: JulieS on
Hi D Pingger,

What other data are you importing? It may be possible that you have
data being imported which conflicts with the % complete. For example,
if you try to import % complete but also import actual and remaining
duration, the percent complete field is going to be recalculated by
the actual and remaining duration values.

Percent complete = (actual duration/duration)*100

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

"D Pingger" <DPingger(a)discussions.microsoft.com> wrote in message
news:0F2EC29E-AE67-4A1D-8CAF-3F7ECED8E6B4(a)microsoft.com...
> In 2003, I'm updating data using an excel spreadsheet but for some
> reason,
> the %complete value doesn't import back in. Is there something I'm
> missing?
>
> I use the import wizard and mapping.
>
> Help!
>
> TIA
> DPingger


From: D Pingger on
Thanks, Julie.

Nope, the only thing I'm importing is a number that goes into Number9 field,
a date that goes into Date9 field and the % complete.

For some reason, it imports the other two but ignores the %complete value.

Any ideas?

Thanks

DPingger

"JulieS" wrote:

> Hi D Pingger,
>
> What other data are you importing? It may be possible that you have
> data being imported which conflicts with the % complete. For example,
> if you try to import % complete but also import actual and remaining
> duration, the percent complete field is going to be recalculated by
> the actual and remaining duration values.
>
> Percent complete = (actual duration/duration)*100
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
> "D Pingger" <DPingger(a)discussions.microsoft.com> wrote in message
> news:0F2EC29E-AE67-4A1D-8CAF-3F7ECED8E6B4(a)microsoft.com...
> > In 2003, I'm updating data using an excel spreadsheet but for some
> > reason,
> > the %complete value doesn't import back in. Is there something I'm
> > missing?
> >
> > I use the import wizard and mapping.
> >
> > Help!
> >
> > TIA
> > DPingger
>
>
>
From: D Pingger on
Hi JulieS,

I tried just importing the % complete field (deleted the other two fields
from the file) and it still wouldn't do it. Hmmmmm. I'm way stumped now.

Help!?!?!?!?!

DPingger

"JulieS" wrote:

> Hi D Pingger,
>
> What other data are you importing? It may be possible that you have
> data being imported which conflicts with the % complete. For example,
> if you try to import % complete but also import actual and remaining
> duration, the percent complete field is going to be recalculated by
> the actual and remaining duration values.
>
> Percent complete = (actual duration/duration)*100
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
> "D Pingger" <DPingger(a)discussions.microsoft.com> wrote in message
> news:0F2EC29E-AE67-4A1D-8CAF-3F7ECED8E6B4(a)microsoft.com...
> > In 2003, I'm updating data using an excel spreadsheet but for some
> > reason,
> > the %complete value doesn't import back in. Is there something I'm
> > missing?
> >
> > I use the import wizard and mapping.
> >
> > Help!
> >
> > TIA
> > DPingger
>
>
>
From: John on
In article <6E032E06-8609-433D-AEB6-A8E12ABB654E(a)microsoft.com>,
D Pingger <DPingger(a)discussions.microsoft.com> wrote:

> Hi JulieS,
>
> I tried just importing the % complete field (deleted the other two fields
> from the file) and it still wouldn't do it. Hmmmmm. I'm way stumped now.
>
> Help!?!?!?!?!
>
> DPingger

DPingger,
Pardon me for nosing in. How is the percent complete value expressed in
Excel? If it is just a number, (i.e. 60 for 60%), Project will not
recognize that format and will import 0%. However, if it is expressed in
Excel as a percent or decimal, (i.e. 60% or .6), then it will be
imported.

John
Project MVP
>
> "JulieS" wrote:
>
> > Hi D Pingger,
> >
> > What other data are you importing? It may be possible that you have
> > data being imported which conflicts with the % complete. For example,
> > if you try to import % complete but also import actual and remaining
> > duration, the percent complete field is going to be recalculated by
> > the actual and remaining duration values.
> >
> > Percent complete = (actual duration/duration)*100
> >
> > I hope this helps. Let us know how you get along.
> >
> > Julie
> > Project MVP
> >
> > Visit http://project.mvps.org/ for the FAQs and additional information
> > about Microsoft Project
> >
> > "D Pingger" <DPingger(a)discussions.microsoft.com> wrote in message
> > news:0F2EC29E-AE67-4A1D-8CAF-3F7ECED8E6B4(a)microsoft.com...
> > > In 2003, I'm updating data using an excel spreadsheet but for some
> > > reason,
> > > the %complete value doesn't import back in. Is there something I'm
> > > missing?
> > >
> > > I use the import wizard and mapping.
> > >
> > > Help!
> > >
> > > TIA
> > > DPingger
> >
> >
> >