Prev: Project - File for each project or File for each person on project
Next: Project - File for each project or File for each person on pro
From: jony on 13 May 2008 11:26 I would like to lock the last task - tape out so it will not be able to update tasks that want to finish after it start -- thanks
From: davegb on 13 May 2008 14:58 On May 13, 9:26 am, jony <j...(a)discussions.microsoft.com> wrote: > I would like to lock the last task - tape out > so it will not be able > to update tasks that want to finish after it start > -- > thanks Not sure what you mean by "lock". Or the rest of your description. Please elaborate so we can help you.
From: jony on 14 May 2008 08:48 Hi I have a tape out milestone date which I cant delay therefore I would like that it will not be possible to make extention for a task that coming before the tape out if its making a delay so I want to "lock" the tape out milestone -- thanks "davegb" wrote: > On May 13, 9:26 am, jony <j...(a)discussions.microsoft.com> wrote: > > I would like to lock the last task - tape out > > so it will not be able > > to update tasks that want to finish after it start > > -- > > thanks > > Not sure what you mean by "lock". Or the rest of your description. > Please elaborate so we can help you. >
From: JulieS on 14 May 2008 14:46
Hi jony, You could set a "Finish No Later Than" constraint on your milestone. Double click on the task and go to the advanced tab. Select the constraint from the drop-down and set your date. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "jony" <jony(a)discussions.microsoft.com> wrote in message news:E3CEC0CD-1F36-4DB6-BCC0-E7DE0E287F35(a)microsoft.com... > Hi > > I have a tape out milestone date which I cant delay > therefore > I would like that it will not be possible to > make extention for a task that coming before the tape out > if its making a delay > > so I want to "lock" the tape out milestone > -- > thanks > > > "davegb" wrote: > >> On May 13, 9:26 am, jony <j...(a)discussions.microsoft.com> wrote: >> > I would like to lock the last task - tape out >> > so it will not be able >> > to update tasks that want to finish after it start >> > -- >> > thanks >> >> Not sure what you mean by "lock". Or the rest of your description. >> Please elaborate so we can help you. >> |