From: dina on 23 Jun 2005 11:18 when I change a resources calendar to reflect vacation, tasks that have been assigned during that time do not move.
From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot on 23 Jun 2005 12:04 Hi Dina, And yet they should! In Tools, Options, Calculation, is calculation set to automatic? Do all other calculations work normally? -- Jan De Messemaeker Microsoft Project MVP +32 495 300 620 http://users.online.be/prom-ade "dina" <dina(a)discussions.microsoft.com> wrote in message news:BABABAE0-3C28-4936-959A-A302C10AF81A(a)microsoft.com... > when I change a resources calendar to reflect vacation, tasks that have > been > assigned during that time do not move.
|