From: ellebelle on
Hello,

Is there a tool in MSProject that shows you when a resource in NOT
allocated to a task. Ideally this would be displayed as a separate task with
splits.

Thanks
From: DavidC on
Hi,

Use 'View\Resource sheet", any resource not allocated to a task will have
'0' in the work column.

Hope this helps.

Regards

DavidC
"ellebelle" wrote:

> Hello,
>
> Is there a tool in MSProject that shows you when a resource in NOT
> allocated to a task. Ideally this would be displayed as a separate task with
> splits.
>
> Thanks
From: "JulieS" <passport6847 at maine dot rr dot on
Hi ellebelle,

I'm not sure I follow your question exactly, but what I think you are
searching for is to try to find out when (what time period) a resource is
not assigned to a task, perhaps due to nonworking time? Have you checked
out either the Resource Usage view (zoomed out to show the appropriate time
scale) or the Resource Graph?

I hope this helps. Let us know how you get along.

Julie
"ellebelle" <ellebelle(a)discussions.microsoft.com> wrote in message
news:48D32988-3B9A-4FF9-9B77-3455032BCDE9(a)microsoft.com...
> Hello,
>
> Is there a tool in MSProject that shows you when a resource in NOT
> allocated to a task. Ideally this would be displayed as a separate task
> with
> splits.
>
> Thanks


From: Steve House [Project MVP] on
The REsource Usage view has an option to display a row of remaining
allocation, that is the difference between what they are allocated and what
their maximum allocation is.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



"ellebelle" <ellebelle(a)discussions.microsoft.com> wrote in message
news:48D32988-3B9A-4FF9-9B77-3455032BCDE9(a)microsoft.com...
> Hello,
>
> Is there a tool in MSProject that shows you when a resource in NOT
> allocated to a task. Ideally this would be displayed as a separate task
> with
> splits.
>
> Thanks

From: ellebelle on
I would like to view it in the gant view as a task.

"Steve House [Project MVP]" wrote:

> The REsource Usage view has an option to display a row of remaining
> allocation, that is the difference between what they are allocated and what
> their maximum allocation is.
>
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
>
> "ellebelle" <ellebelle(a)discussions.microsoft.com> wrote in message
> news:48D32988-3B9A-4FF9-9B77-3455032BCDE9(a)microsoft.com...
> > Hello,
> >
> > Is there a tool in MSProject that shows you when a resource in NOT
> > allocated to a task. Ideally this would be displayed as a separate task
> > with
> > splits.
> >
> > Thanks
>
>